Module 15 - Earned Value Management Flashcards

(73 cards)

1
Q

What does Earned Value Management (EVM) measure?

A

Project performance and progress

EVM compares planned work with completed work to forecast performance problems.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name the three key data elements in Earned Value Analysis.

A
  • Actual Cost of Work Performed (ACWP)
  • Budgeted Cost of Work Performed (BCWP)
  • Budgeted Cost of Work Scheduled (BCWS)

These elements are essential for conducting earned value analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

True or false: EVM ties directly to cost estimating.

A

FALSE

EVM provides data that cost estimators often use, but it does not directly tie to cost estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of an Earned Value Management System (EVMS)?

A

A multi-faceted management planning tool

EVMS integrates technical scope with time-phased cost or budget for program planning and execution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Fill in the blank: EVM provides a framework to conduct integrated planning and execution, helping program managers understand _______.

A

problem areas

This understanding allows for mitigation of cost overruns and schedule delays.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the practical applications of EVM for a cost estimator?

A
  • Developing more accurate Estimates At Complete (EACs)
  • Predicting costs for analogous programs
  • Developing cost estimating relationships

These applications enhance the accuracy of cost estimations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Program Management Baseline (PMB)?

A

The baseline against which EVM is employed

A good PMB is developed using a resource-loaded schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does Level of Effort (LOE) refer to in EVM?

A

Support activities of short duration which are periodically repeated

LOE tasks have less technical integration compared to discrete EVM methods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Control Account (CA) in EVM?

A

Work assigned to one organizational element on one CWBS element

CAs are the focal point for accumulating actual costs and comparing them to BCWP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the role of a Control Account Manager (CAM)?

A

Responsible for managing work and tracking EV data

The CAM analyzes earned value metrics and reports on variances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the Work Breakdown Structure (WBS)?

A

A hierarchical structure that organizes project tasks

The WBS is critical for managing and reporting project performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

True or false: EVM is best suited for projects with open-ended or undefined objectives.

A

FALSE

EVM is best for projects with defined deliverables and strict budget limits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the Integrated Baseline Review (IBR)?

A

A review to assure the baseline supports program success

The IBR occurs early in the program’s life.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fill in the blank: EVM provides an early warning of _______ or schedule issues.

A

cost

This early tracking improves project accountability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the benefits of using EVM?

A
  • Early warning of cost or schedule issues
  • Clear definition of work scope
  • Objective measurement and analysis

These benefits enhance project management effectiveness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the significance of Earned Value (EV) in project tracking?

A

It adds a new dimension by measuring work accomplished

EV helps determine if the project is on track regarding cost and schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are Work Packages in project management?

A
  • Detailed, short-span tasks
  • Typically last four to six weeks
  • Required to accomplish CA objectives

Planning Packages entail future work yet to be planned in detail as work packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What factors determine the decision to detail plan all work versus only near-term work?

A
  • Size of the project
  • Scope of the project
  • Complexity of the project
  • Oversight requirements

Some projects detail plan the entire effort up front rather than working a rolling wave of detail planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

List the resources required to complete work effort in work packages.

A
  • Direct labor
  • Material
  • Other Direct Charges (ODCs)

Resources are assigned to each work and planning package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What does BCWS stand for in Earned Value data elements?

A

Budgeted Cost of Work Scheduled

It represents the plan consisting of time-phased dollars associated with work packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the Budgeted Cost of Work Performed (BCWP)?

A

The value earned by the work performed to date

Also known as Earned Value (EV).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What does ACWP represent?

A

Actual Cost of Work Performed

It is calculated based on the contractor’s accounting system records.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Define Budget at Complete (BAC).

A

The baseline plan for the entire effort

It represents the sum of all planned work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the Latest Revised Estimate (LRE)?

A

The most current approximation of what it will cost to complete all work

Often referred to as the Estimate at Completion (EAC).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is the **Performance Measurement Baseline (PMB)**?
The total baseline against which EV is tracked ## Footnote It includes a bucket of money called Undistributed Budget (UB).
26
What is the purpose of **Management Reserve (MR)**?
Covers unanticipated in-scope changes ## Footnote It is set aside by the Program Manager and varies depending on project risk.
27
What does the **Contract Budget Base (CBB)** represent?
PMB plus MR ## Footnote It represents the total cost of the work.
28
What are the **five common methods** to measure Earned Value?
* Milestones * Percent complete * 0/100 * 50/50 * Level of Effort ## Footnote Each method is determined based on the type of work encompassed.
29
What does **Schedule Variance (SV)** measure?
The dollar representation of the difference between BCWP and BCWS ## Footnote It indicates whether the project is ahead or behind schedule.
30
Define **Cost Variance (CV)**.
The difference between BCWP and ACWP ## Footnote A positive CV indicates the project is under cost.
31
What is **Variance at Complete (VAC)**?
The difference between planned cost to complete the work and expected cost to complete the work ## Footnote VAC = BAC - LRE.
32
True or false: A positive **Schedule Variance (SV)** indicates a project is behind schedule.
FALSE ## Footnote A positive SV indicates the project is ahead of schedule.
33
What should analysts focus on when reviewing **variances**?
* Cumulative data points * Current data points * Sudden trend changes ## Footnote Variances over 10% are considered significant and require examination.
34
What is the **0/100 method** used for in performance measurement?
100% of performance is taken when the task is complete ## Footnote Best for very short work packages.
35
What does **Level of Effort (LOE)** measure?
Performance is planned and earned using a straight-line approach ## Footnote It is primarily reserved for more time-related work.
36
What should analysts do regarding **variances** in data?
Review and understand variances, explain and manage them ## Footnote Variances are natural and should not be eliminated.
37
What does a **negative cost variance** indicate?
CPI less than one ## Footnote A CPI of 0.9 means that for every $1.00 spent, the program gets 90 cents worth of work completed.
38
What is the **Cost Performance Index (CPI)**?
The ratio of work performed to cost of performing the work ## Footnote A CPI greater than one corresponds to a positive cost variance.
39
What does the **Schedule Performance Index (SPI)** measure?
The ratio of work performed to work planned ## Footnote An SPI less than one corresponds to a negative schedule variance.
40
What are the **cumulative BCWS**, **BCWP**, and **ACWP** for the aquarium example?
* BCWS: $400 * BCWP: $200 * ACWP: $300 ## Footnote These values help assess project performance.
41
What does a **negative Schedule Variance (SV)** imply?
The project is behind schedule ## Footnote SV is calculated as the difference between BCWP and BCWS.
42
What is the **Variance at Completion (VAC)**?
The difference between the original budget and the latest revised estimate ## Footnote A negative VAC indicates an expected cost overrun.
43
What should be considered when analyzing **percentages** in EV analysis?
* % Planned = BCWS/BAC * % Complete = BCWP/BAC * % Spent = ACWP/BAC ## Footnote These percentages help assess project performance against the budget.
44
What does it indicate if **BCWS = BCWP = ACWP**?
EV is not really being used ## Footnote This situation may occur in Level of Effort (LOE) tasks.
45
What is the **Management Reserve (MR)** used for?
To cover unfavorable cost variances ## Footnote MR should not be used without examining the course of action.
46
What does a **CPI of 0.67** mean?
For every dollar spent, 67 cents of value is received ## Footnote This indicates a negative cost performance.
47
What is the significance of **thresholds** in variance reporting?
Thresholds govern the variance reporting process ## Footnote Common thresholds include percentages and absolute dollars.
48
What should variance reports focus on?
* Where is the variance? * What is the cause? * What is the impact? * What is the Action Plan? ## Footnote These elements help in managing the program effectively.
49
What does a **BAC < 0** indicate?
Should never happen ## Footnote It implies the contractor is going to give money to the government for work performed.
50
What is the purpose of **variance action plans**?
To capture and track necessary actions promptly ## Footnote This ensures the program takes actions to mitigate risks.
51
What does it mean if **percent spent** is much greater than **percent complete**?
The project is significantly overrunning on its cost budget ## Footnote This indicates potential financial issues.
52
What should be done if a contractor expects to build six aquariums next month after building two in one month?
Question how they plan to accomplish this work ## Footnote Analysts should assess the feasibility of the contractor's expectations.
53
What is the **impact of using MR** on project performance?
It can indicate problems if used excessively ## Footnote Graphing MR balance against project metrics helps visualize trends.
54
What does **ACWP > 0 but BCWP = 0** indicate?
Costs incurred without performance ## Footnote This situation should not occur in a well-managed EVMS.
55
What is the **formula for calculating EAC**?
EAC = BAC / CPI ## Footnote This formula helps project future performance based on current metrics.
56
What does a **positive variance** represent?
An area of opportunity ## Footnote Funds could be reallocated to improve project outcomes.
57
What is the **Estimate At Complete (EAC)** used for?
* Identify cost drivers and take corrective action * Ensure contract ceiling and program budget limits are sufficient * Avoid overpaying progress payments ## Footnote EAC is crucial for managing project costs effectively.
58
What are the **two common methods** to project an independent EAC?
* CPI forecast * CPI-SPI forecast ## Footnote These methods utilize past performance data to estimate future costs.
59
The **CPI forecast** assumes what about the cumulative CPI?
It will remain constant throughout the program ## Footnote This is often referred to as the best-case forecast.
60
What does the **CPI-SPI forecast** consider in its calculation?
The schedule ## Footnote This forecast is often referred to as the worst-case forecast.
61
Calculate the **CPI forecast** using the formula: CPI Forecast = ACWP + BCWR / CPI = BAC / CPI. If BAC is 800 and CPI is 0.67, what is the EAC?
1200 ## Footnote This calculation assumes a constant CPI of 0.67.
62
What does **TCPI** stand for?
To-Complete Cost Performance Index ## Footnote TCPI measures the performance required to meet a specific cost target.
63
What is the formula for **TCPIBAC**?
TCPIBAC = BCWR / (BAC – ACWP) ## Footnote This formula helps determine the performance needed to meet the Budget At Completion.
64
If **TCPI** is lower than **CPI**, what does it indicate?
Productivity is expected to be lower in the future ## Footnote This situation requires investigation into potential causes of decreased productivity.
65
If **TCPI** is higher than **CPI**, what does it suggest?
Productivity is expected to increase in the future ## Footnote This may indicate optimistic assumptions about future performance.
66
What is the **CPI-SPI forecast** formula?
CPI - SPI Forecast = ACWP + BCWR / (CPI*SPI) ## Footnote This formula factors in both cost and schedule performance.
67
What is the **significance of graphing EACs** with BAC and LRE?
It adds context to the analysis ## Footnote Graphing trends over time helps visualize performance and forecast accuracy.
68
What does the **LRE** represent?
Latest Revised Estimate ## Footnote LRE includes the contractor’s best estimate and assessment of risk.
69
What is the **best-case EAC** based on the CPI forecast if the BAC is 800 and CPI is 0.67?
1200 ## Footnote This assumes a constant CPI of 0.67.
70
What is the **worst-case EAC** based on the CPI-SPI forecast if SPI is 0.5?
2100 ## Footnote This includes the actuals to date and factors in the schedule performance.
71
What does it mean if **ACWP** exceeds either the **BAC** or **LRE**?
It usually indicates nearing task completion ## Footnote This can also occur due to unprocessed ECPs.
72
What is a major benefit of using **EVM**?
* Improved planning * Objective performance measurement * Accurate forecasting of cost to complete ## Footnote EVM integrates technical scope with schedule and budget for better management.
73
True or false: The **real key to a successful EVMS** is the partnership and dialogue between the government and the contractor.
TRUE ## Footnote This collaboration fosters ownership and responsibility in project success.