Find the swell of a soil that weighs 2800 lb/cu yd (1661 kg/m’) in its natural state and 2000 lb/cu yd (1186 kg/m*) after excavation.
40%
Find the shrinkage of a soil that weighs 2800 lb/cu yd (1661 kg/m’) in its natural state and 3500 lb/cu yd (2077 kg/m’) after compaction.
20%
(MAY 2018, NOV 2018) A soil weighs 1960 /BCM), and 3500 lb/CCY (2077 kg/CCM). (a) Find the load factor and shrinkage fact for the soil. (b) How many bank cubic var (BCY) or meters (BCM) and compacted cubic yards (CCY) or meters (CCM) are contained in 1 million loose cubic yards (593,300 LCM) of this soil?
(a) Load Factor = 0.70, Shrinkage Factor = 0.80 (b) Bank Volume = 700,000 BCY or 415,310 BCM, Compacted Volume = 560,000 BCY or 332,248 BCM
(MAY 2019) Find the base width and height of a triangular spoil bank containing 100 BCY (76.5 BCM) if the pile length is 30 ft (9.14 m), the soil’s angle of repose is 37°, and its swell is 25%.
B = 7.45 m, H = 2.80 m
Find the base diameter and height of a conical spoil pile that will contain 100 BCY (76.5 BCM) of excavation if the soil’s angle of repose is 32° and its swell is 12%.
D = 10.16 m. H = 3.17 m
Estimate the volume of excavation required (bank measure) for the basement shown in Figure 3. Values shown at each corner are depths of excavation. All values are in feet (m).
146.6 BCM
Find the volume (bank measure) of excavation required for a trench 3 ft (0.92 m) wide, 6 ft (1.83 m) deep, and 500 ft (152 m) long. Assume that the trench sides will be approximately vertical.
255 BCM
Find the volume of excavation required for the area shown in Figure 4. The figure at each grid intersection represents the depth of cut at that location. Depths in parentheses represent meters.
14,596 BCM
(MAY 2022) Estimate the actual bucket load in bank cubic yards for a loader bucket whose heaped capacity is 5 cu yd (3.82 m3). The soil’s bucket fill factor is 0.90 and its load factor is 0.80.
2.75 BCM
(APR 2024, NOV 2023, MAY 2022, NOV 2021) Find the expected production in loose cubic yards (LCM) per hour of a small hydraulic excavator. Heaped bucket capacity is 3/4 cu yd (0.57 m3). The material is sand and gravel with a bucket fill factor of 0.95. Job efficiency is 50 min/h. Average depth of cut is 14 ft (4.3 m). Maximum depth of cut is 20 ft (6.1 m) and average swing is 90.
113 LCM/h
Find the expected production in loose cubic yards (LCM) per hour of a 3-yd (2.3-m3) hydraulic shovel equipped with a front-dump bucket. The material is common earth with a bucket fill factor of 1.0. The average angle of swing is 75° and job efficiency is 0.80.
290 LCM/h
Determine the expected dragline production in loose cubic yards (LCM) per hour based on the following information: Dragline size = 2 cu yd (1.53 m3) Swing angle = 120° Average depth of cut = 7.9 ft (2.4 m) Material = common earth Job efficiency = 50 min/h Soil swell op = 25%.
165 LCM/h
Estimate the production in loose cubic yards per hour for a medium-weight clamshell excavating loose earth. Heaped bucket capacity is 1 cu yd (0.75 m3). The soil is common earth with a bucket fill factor of 0.95. Estimated cycle time is 40 s. Job efficiency is estimated at 50 min/h.
53 LCM/h
(NOV 2022, NOV 2019) A wheel tractor-scraper weighing 100 tons (91 t) is being operated on a haul road with a tire penetration of 2 in. (5 cm). What is the total resistance (Ib and kg) and effective grade when the scraper is ascending a slope of 5%; the scraper is descending a slope of 5%?
9,100 kg, 10%
(NOV 2022) A wheel tractor-scraper weighing 100 tons (91 t) is being operated on a haul road with a tire penetration of 2 in. (5 cm). What is the total resistance (Ib and kg) and effective grade when the scraper is descending a slope of 5%?
0 kg, 0%
(MAY 2022) A crawler tractor weighing 80,000 lb (36 t) is towing a rubber-tired scraper weighing 100,000 lb (45.5 t) up a grade of 4%. What is the total resistance (Ib and kg) of the combination if the rolling resistance factor is 100 lb/ton (50 kg/t)?
5,535 kg
(APR 2023, MAY 2022) A power-shift crawler tractor has a rated blade capacity of 10 LCY (7.65 LCM). The dozer is excavating loose common earth and pushing it a distance of 200 ft (61 m). Maximum reverse speed in
third range is 5 mi/h (8 km/h). Estimate the production of the dozer if job efficiency is 50 min/h.
271 LCM/h
Estimate the hourly production in loose volume (LCY and LCM) of a 31/2-yd (2.68-m3) wheel loader excavating sand and gravel (average material) from a pit and moving it to a stockpile. The average haul distance is 200 ft (61 m), the effective grade is 6%, the bucket fill factor is 1.00, and job efficiency is 50 min/h.
168 Lm’/h (Actual Board: 178 Lm’/h)
The estimated cycle time for a wheel scraper is 6.5 min. Calculate the number of pushers required to serve a fleet of nine scrapers using single pushers. Determine the result for both backtrack and chain-loading methods.
2 and 3
Find the expected production of the scraper fleet of Example 10 if only one pusher is available and the chain-loading method is used. Expected production of a single scraper assuming adequate pusher support is 226 BCY/h (173 BCM/h).
1,112 BCM/h
Given the following information on a shovel/truck operation, (a) calculate the number of trucks theoretically required and the production of this combination; (b) calculate the expected production if two trucks are removed from the fleet.
(a) Il trucks and 212 BCM/h (b) 186 BCM/h
Fifteen miles (24.1 km) of gravel road require reshaping and leveling. You estimate that six passes of a motor grader will be required. Based on operator skill, machine characteristics, and job conditions, you estimate two passes at 4 mi/h (6.4 km/h), two passes at 5 mi/h (8.0 km/h), and two passes at 6 mi/h (9.7 km/h). If job efficiency is 0.80, how many grader hours will be required for this job?
23.1 h
Trial blasting indicates that a rectangular pattern of drilling using 3-in. (7.6-cm) holes spaced on 9-ft (2.75-m) centers and 20 ft (6.1 m) deep will produce a satisfactory rock break with a particular explosive loading. The effective hole depth resulting from the blast is 18 ft (5.5 m). Determine the rock volume produced per foot (meter) of drilling.
6.8 m’/m