Four influencing factors of cost projection
What is included in life cycle costs?
Operational costs, maintenance costs, taxes, financing, replacement, and renovation.
Modification
Percentage fee
Compensation based on a percentage of construction costs; it is applicable to either construction contracts or professional service agreements.
One of the proposed HVAC system options for a project has an upfront cost of $12,000 with an estimated life span of 15 years and a salvage value of $1,500. What is the annual depreciation of the system?
$700: $12,000 (upfront cost) − $1,500 salvage value = $10,500, divided by life span of 15 years = $700 annual depreciation.
Residual value
The remaining value of a system or component at replacement or the end of a study period. This includes the salvage value, resale value, or scrap value less the disposal and/or conversion costs.
Annually recurring fixed cost vs. annually recurring escalating cost
Annually recurring fixed cost is a fixed payment service contract that includes the cost of inflation over time. Annually recurring escalating cost, on the other hand, is a bit more difficult to accurately predict because it includes service and maintenance, which involves increasing amounts of work, as well as frequent replacements that escalate at a rate different than inflation.
OM&R
In life cycle cost calculating, the OM&R value refers to the operation, maintenance, and repair cost. This value does not include fuel operating costs.
What are the three types of cost periods in a life cycle cost analysis (LCCA)?
Value engineering
An organized effort directed at analyzing designed building features, systems, equipment, and material selections for the purpose of achieving essential functions at the lowest life cycle cost consistent with required performance, quality, reliability, and safety.
Cost-saving measures
True or False? Preliminary design decisions are usually not significant in the overall determination of a project because everything can always be changed.
False. As a project progresses from broad strokes to detailed parts, the possibility of going back to readdress previously made decisions disrupts the progress of the work. Therefore, the preliminary design is often considered the most sensitive and requires the most sound and experienced judgment to execute.