How much load needs to be shed per 1.0 Hz?
6%-10%
Uncontrolled loss of firm load for greater than 15 minutes from a single incident is how many MW?
Greater than 300 MW for entities with previous year’s peak demand greater than 300 MW
OR
Greater than 200 MW for all other entities
ACE Equation
ACE = (Actual Net Interchange - Scheduled Net Interchange) - 10B(Actual Frequency- Scheduled Frequency) - Interchange Meter Error
B = Frequency Bias Setting
Exporting Power
Positive
Importing power
Negative
Zone 1 covers how much percent of the line?
75-80%
Zone 2 covers how much of the line?
100-120%