A. Inspiration-related currency
B. Position-related currency
C. Relationship-related currency
D. Task-related currency
1.
Correct Answer: B
A. Feedback
B. Computer-based
C. Mentoring
D. Coaching
2.
Correct Answer(s): B
C
D
A. To help the team work through a temporary setback.
B. To help the team to overcome a lack of confidence.
C. To accomplish early “wins” in the project’s life cycle.
D. To ensure that there are no activities that have late start criteria.
3.
Correct Answer(s): A
B
C
A. Project schedule
B. Status review system
C. Work authorization system
D. PMIS
4.
Correct Answer: C
A. Work done is in line with the project goals.
B. What work to be done is clearly outlined.
C. Who is to do the work.
D. When the work is to begin and end is understood.
5.
Correct Answer(s): B
C
D
A. Metrics
B. Control limits
C. PCIs
D. COQ
6.
Correct Answer: A
A. Project management information system
B. Communications plan
C. Project management enterprise software
D. Communications and feedback system
7.
Correct Answer: A
A. Completed and incomplete deliverables.
B. Actual conformance to quality plan.
C. Intended performance details of the work to be completed.
D. ETC for scheduled activities that have started.
8.
Correct Answer(s): A
B
D
A. Conforming product specifications to customer requirements.
B. Strategizing how to create products that meet quality requirements.
C. A pattern of activities which ensure that the product meets quality requirements.
D. A set of tactics used to determine if goods meet quality requirements.
9.
Correct Answer: C
A. Contains an approved quality audit methodology.
B. Ensures that efficient or effective processes and procedures are used.
C. Contains future change recommendations.
D. Determines whether the project complies with organizational and project policies, processes, and procedures.
10.
Correct Answer(s): A
C
D
A. That the team members are distributed geographically.
B. That the team is located in one physical location.
C. That the team uses a war room.
D. That the team members work from home.
11.
Correct Answer: B
A. Required so that team members do not over-write one another’s work.
B. Not a problem for project managers who use adequate backup systems.
C. Required to make sure everyone is working with the same, most recent document.
D. Required to maintain only the latest version of the document.
12.
Correct Answer: C
A. A team that manages multiple projects concurrently.
B. The same as the office of the CEO.
C. A unit that centralizes and coordinates the management of projects.
D. An organization that may provide project support functions.
13.
Correct Answer(s): C
D
A. Are only done at the end of the project.
B. Check the fitness of the project’s output or the fitness of the quality plan.
C. Are done only once during the entire project life cycle.
D. Are best done at random intervals over the course of the project.
14.
Correct Answer(s): B
D
A. To evaluate whether the project output is fit for the purpose it was intended.
B. To evaluate if best practices identified in the previous projects have been implemented.
C. To evaluate whether the quality management plan is still appropriate after quality improvements have been made.
D. To evaluate if the quality assurance team members are qualified
E. To evaluate how statistical process control may be used to improve the capability of a process.
15.
Correct Answer(s): A
C
E
A. Assess for risk to project success.
B. Subject them to trade-off analysis.
C. Ensure that the change does not affect the project scope.
D. Determine the cost of quality.
16.
Correct Answer(s): A
B
A. Creating a margin of error for product specifications.
B. Preventing problems, rather than fixing them.
C. Establishing upper and lower specifications for products.
D. Increasing production rates by providing training for quality control inspectors.
17.
Correct Answer: B