Performance certificates
Evaluate work that has been done and put a figure on it to say “this is what is owed for work done thus far”
Certificates
Hire third party to issue certificates for payment/performance
Interim payment certificate
- Subject to adjustment
Final Payment Certificates
- Owners obliged to pay what is certified
Amount certified for payment
Must calculate according to contract and what it says to consider
Common law deductions from progress payments
- Deductions for defective work
Renumeration
- Contract specifies type, amount, and timing
Entire vs partial completion
Pay when paid clauses
Statutory Declaration
Saying that all contractors and subs have been paid (all people beneath you)