What is a contract sum?
The contract sum is the amount (or consideration) that the employer agrees to pay the contractor for carry out the works. Found in Article 2
What items are able to adjust a contract sum?
When would you NOT make an adjustment to the Contract Sum?
What is provisional sum?
A Provisional Sum is an allowance for a specific element of works that has not been defined in the tender documents.
What are the 2 types of provisional sums?
2 types of Provisional Sum in the JCT contract:
What is VAT?
Value added tax, or VAT, is the tax you have to pay when you buy goods or services.
Is VAT included in the Contract Sum?
NO, the Contract Sum is VAT-exclusive. The Employer shall in additional to each monthly interim payment pay the amount of any VAT properly chargeable.
What is the Construction Industry Scheme (CIS)?
What is retention?
When is retention released?
Half retention is released to the Contractor when practical completion or partial possession is achieved, and the other half is released when the certificate of making good defects is issued at the end of the rectification period.
What are the rules on treatment of retention?
Statement of the amount of retention to be deducted from each Gross Valuation is required to be sent to the contractor prior to issue of Interim Certificate.
What is a retention bond?
A retention bond is financial security provided by an insurer company / bank to secure the amount that would have been held as retention. The value of the bond will reduce by half after practical completion has been certified.
What is the typical value of a retention bond?
3 or 5 % of the contract sum
How are bonds paid for?
Bonds are paid for by the Contractor but the costs for doings so may be included within Contractors tenders
What is the purpose of retention?
To safeguard the Employer against latent defects and incentivize the Contractor to ensure works are completed on time and not defective.
What are Fluctuations?
Provisions in Construction Contracts to provide a mechanism for dealing with the effects of inflation – if large projects lasts a few years this is very crucial. They allow for: • Changes in taxation • Costs of labour • Materials • Admin Costs
Hoes does JCT deal with fluctuations?
Under Schedule 7 – Fluctuation Option A, B, C
• Option A: contribution, levy and tax fluctuations
• Option B: Labour and material cost and tax fluctuations
• Option C: formula adjustments
Chosen option is stated in the Contract Particulars
What are the Advance Payments?
When can payment on an advanced payment bond be made under JCT?
Payment shall only be made when the Contractor provides the Employer a bond in the terms set out in Schedule 6.
When may you use an advance payment notice?
Where are the details for advance payment stated?
Contract Particulars and Section 5 (JCT) or Contract Data and Option X14 (NEC)
What does the Construct Act say about payment provisions?
The Construction Act (HGCRA96) states that every contract must provide for interim payments if the contract period is greater than 45 days and, for every payment, a mechanism for calculating the sum due, the due and the final date for payment.
How can Interim Payment calculations be calculated?
The way interim payments are calculated will be stated within the Contract Particulars. (Contract Data NEC)
• Periodic (Interim) Payments
o Most used method of payment.
o Assessment of works to date, against the submitted pricing document (i.e. BQ/Schedule of Works/Contract Sum Analysis).
o 1st interim payment normally due 1 month after the date of possession.
o Aids client cash flow instead of lump payments for stages/milestones.
• Stage Payments
o Stages are typically related to the completion of significant elements of works (i.e. substructure).
o Typically used when no QS is involved.
• Milestone Payments
o A variant of Stage Payments, whereby the Contractor is paid for completion of milestones.
o this may be a particular element (substructure, frame, façade)
o will be set against a pre-agreed Programme dates.
• Activity Schedule
o commonly used in lump sum contracts and NEC Option A&C.
o works priced to be undertaken in completing the works.
o can only be certified once 100% of activity is complete.
What are preliminaries?