What does WSJF stand for?
“Weighted Shortest Job First”
What is the WSJF formula?
WSJF = [Cost of Delay] / [Job Duration]
==OR==
WSJF = [(User-Business Value) + (Time Criticality) + (RR or OE)] / [Job Duration]
What 3 values are used to calculate the Cost of Delay?
User-business value – What is the relative value to the customer or business? Do our users prefer this over that? What is the revenue impact on our business? Is there a potential penalty or other negative effects if we delay?
Time criticality – How does the user/business value decay over time? Is there a fixed deadline? Will they wait for us or move to another solution? Are there Milestones on the critical path impacted by this? What is the current effect on customer satisfaction?
Risk reduction-opportunity enablement value – What else does this do for our business? Does it reduce the risk of this or a future delivery? Is there value in the information we will receive? Will this feature enable new business opportunities?
What are the 5 PI events that occur at the Team level?
What are the 5 PI events that occur at the ART level?
What are the 7 PI events that occur at the Solution level?
What are the Goals, Inputs, and Outputs of Pre-PI Planning?
What are the Goals, Inputs, and Outputs of Post-PI Planning?
The Inspect & Adapt Event is made of what 3 parts?
What happens in the “Quantitative and Qualitative Measurement” phase of the I&A Event?
What happens during a “Retrospective and Problem-Solving Workshop”?