Pjm Flashcards

(16 cards)

1
Q

What are the three distinct branches of project delivery models?

A
  • Design-Bid-Build
  • Design-Build
  • Integrated Project Delivery

Each model has unique characteristics and is suited for different project needs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In the Design-Bid-Build model, who prepares the Construction Documents?

A

Architect

The Architect also acts as an agent for the Owner and administers construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the primary responsibility of the Construction Manager (CM) in the CM-Advisor model?

A

Advising the Owner

The CM does not build but consults on constructibility and cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In the Design-Build model, who has comprehensive responsibility for design and execution?

A

Design-Build entity

This entity develops the design and proposes a contract sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does CM-Agent do differently compared to CM-Advisor?

A

Assumes more authority

The CM-Agent coordinates design and construction teams under an agency agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the GMP in the context of CM-Constructor?

A

Gross Maximum Price

It is a contractually guaranteed price for construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Single Purpose Entity in project delivery?

A

Independent LLC for one project

All risk and reward is shared, ensuring a fully integrated process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Multi-Party Agreement?

A

One agreement between Architect, Owner, and Contractor

Savings are shared if the final cost is less than the target cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In a Project Alliance, how are team profits structured?

A

Dependent on successful completion of project goals

Liability to one another is waived, and no dispute resolution mechanisms are provided.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the main advantage of competitive bidding in project delivery?

A

Reduces cost

It ensures well-defined roles and minimal coordination.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

True or false: In the Design-Bid-Build model, design is finished before construction discussions begin.

A

TRUE

This can lead to adversarial relationships and a higher likelihood of claims.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the primary disadvantage of the Design-Build model?

A

Owner has less control over design and quality

This is due to the absence of an Architect acting as a separate check.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the project phases in project delivery?

A
  • Conceptualization
  • Criteria Design
  • Detailed Design
  • Implementation Documents
  • Agency Review, Buyout
  • Construction
  • Closeout

These phases outline the progression of a project from inception to completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the role of specialty contractors in the design phase?

A

Develop complex or proprietary construction details

They are included early to ensure accurate design execution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does Design-Assist Contracting involve?

A

Specialty contractors included early in design

This approach enhances collaboration and efficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Relational Contract?

A

Limits liabilities but doesn’t waive everything

The Owner is responsible for final decisions when there is no consensus.