Planning Process Flashcards

(39 cards)

1
Q

The planning Process Group is for

A

Establish Total Scope

Prgressive Elaboration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is in the Integration of planning

A

Making Objective Trade Off’s

-Scope, Schedule, Cost, Quality, Risk, Resources

PM responsible for integration

Develops course of action

Deveolps PM Plan & Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

For Itereative Planning

A

Team members create WBS

Additional team members added

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Agile Planning is described as

A

Promote team as experts

control team

collaborative decision making

Team broad skill base

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the difference between

Project Scope vs Product Scope

A

Project

Product

WORK that has to be done

Measured against project management plan

DELIVERABLE

Features and functions

Measured against product requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Stakeholder Engagement Includes

A

Develop HOW to involve stakeholders

Needs, Interest, Impact, Expectations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Inputs for Stakeholder Engagement

A

Project Charter

Stakeholder Register

PM Plan

EEF & OPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Outputs for Stakeholder Engagement

A

Stakeholder Engagement Plan

Desired vs Current engagement levels

Communication Requirements

Discretion distributing sensitive info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SEAM stands for

A

Stakeholder Engagement Assessment Matrix

Compare and Document current vs desired engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

SEAM Matrix

Stakeholder Engagment Assessment Matirx

A

Stakeholder

Unaware

Resistant

Neutral

Supportive

Leading

Joe

Current ©

Desired (D)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Describe Plan Scope Management

A

How scope will be defined, validated, and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Inputs to Plan Scope Management

A

Project Charter

PM Plan

EEF & OPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Outputs for Plan Scope Management

A

Scope Management Plan

Requirments Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Scope Management Plan Describes

A

How to prepare scope statement

create WBS

How scope is validated, approved, controlled, and changed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Requirements Management Plan describes

A

How requirements planned

how changes will be managed

product metrics

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Agile Plan Scope Management

A

Deliverables developed over multiple iterations

product backlog

highest priority items delivered

more time spent on refinement

Release versions

Customer is continuously engaged

17
Q

Collect Requirements

A

Determine/Document Stakeholder needs and requirements

18
Q

Inputs to Collect Requirements

A

Project Charter

Business Documents

Stakeholder Register

PM Plan

EEF & OPA

19
Q

Outputs to Collect Requirements

A

Requirements Documentation

Requirements Traceability Matrix

20
Q

Data Gathering for Requirements Collection

A

Interviews (PM Job)

Focus Groups

21
Q

4 interpersonal requirement techniques

A

Facilitation (QFD, JAD, User Stories)

Workshops (Cross Functional, Reconcile Differences)

Observation (Job Shadowing)

Nominal Group Technique NGT (Voting Process)

22
Q

Data Representation Techniques

A

Affinity Diagram

Mind Mapping

Context Diagrams

23
Q

Tools and Techniques to Collect Requirements

A

QFD Quality Function Deployment

-Voice of Customers

JAD Joint Application Development

-Bring business SME’s and developers work together

HOQ House of Quality

24
Q

What are the 4 interpersonal techniques to gather information

A

Facilitation

Observation

Workshops

Nominal Group Technique

25
Facilitation includes what 3 things
**QFD** - Quality Function Deployment (Voice of Customer, Needs are sorted and prioritized) **JAD** - Joint Application Development (SME's and developers work otgether) **User Stories** (Required functionality)
26
what are the 5 Decision making techniques
Unanimity - Everyone agrees Majority - \>50% agrees Plurality - Largest Block agrees Autocratic - One persons choice MCDA (Multi Criteria Decision Analysis) - Decision Matrix
27
Define Scope
Detailed description of the project / product (Scope Statement)
28
Inputs to define Scope
Project Charter PM Plan Project Documents EEF and OPA
29
Outputs for Define Scope
Project Scope Statement Project Document Updates -Assumption Log
30
Tools and techniques to Define Scope
Expert Judgment Product Analysis Data Analysis Decision Making (MCDA)
31
What are the 6 tools for Product Analysis (Alternatives Analysis)
Value Analysis - Lowest cost without loss of quality.. Functional Analysis - Function based word pair (remove pollutants) PBS - Product Breakdown Structure - Hierarchy of product Requirements Analysis - Elicit Systems Analysis - desing related Systems Engineering - Design and managmenet of engineering projects
32
What are the ouputs to the Scope Statement
Provides common understanding to stakeholders Describes all deliverables Inlcudes scope exclusions or boundaries Product or project scope description product acceptance criteria Assumptions - factors considered to be true Constraints -Limiting Factors
33
Difference between Charter and Scope Project Charter vs Scope Statement
Charter Scope Statement **High Level Summary** **Detailed** **Project purpose justification** Scope description Measureable objectives Product acceptance Success criteria Deliverables High level requirements Scope Exclusions High level description Assumptions Schedule and budget summary Constraints Stakeholder list **Elaborates the Charter** Approval requirements Assign PM Authorizing persons names
34
Describe WBS Work Breakdown Structure
Subdivide project deliverables into smaller more manageable componenets or packages
35
Inputs to WBS
Project Documents (Scope / Requirements) PM Plan EEF and OPA
36
Outputs to WBS
Scope Baseline Which includes WBS, WBS Dictionary **Updates** project documents
37
Decomposition of WBS _This is on the TEST_
Hierarchical down to package level Work Package is lowest level of WBS Deliverables can have different levels of breakdown Agile: Epics are decomposed to user stories WBS must include project management work component Code of Accounts Decomp could have phases, deliverables, sub projects as first level of WBS 100% Rule: WBS defines total scope of the project
38
WBS Notes
Created by Project Team Team development tool not time based; deliverable oriented communication between team and stakeholders WBS Dictionary Control Account - Management point Planning Package Heuristic - a rule of thumb Baseline Scope Baseline = WBS + WBS Dictionary + Scope Statement