What does PMI mean by business documents?
A. Business Case
B. Project Business Management Plan
C. Project Benefits Management Plan
D. Business Draft
A. Business Case
C. Project Benefits Management Plan
________ is time-limited (it has a definite beginning and end). Is unique (it has not been attempted before by this organization).
A. Phase
B. Project
C. Portfolio
D. Process
E. Program
B. Project
The following are part of what plan?
Target Benefits
Strategic Alignment
Timeframe for realizing benefits
Benefits Owner
Metrics
Assumptions
Risks
A. Project Management Benefits Plan
B. Project Business Benefits Plan
C. Project Management Plan
D. Program Business Benefits Plan
B. Project Business Benefits Plan
All of the following are part of what?
-Name and authority of the sponsor or other person(s) authorizing the project charter
Project Charter
What does the acronym “WAS” stand for?
Work Authorization System
What 3 items make up the Performance Measurement Baseline? (Choose 3)
A. Cost Baseline
B. Project Baseline
C. Schedule Baseline
D. Scope Baseline
E. Requirements Baseline
A. Cost Baseline
C. Schedule Baseline
D. Scope Baseline
The following points belong to which management plan?
Scope Management Plan
The following points belong to which management plan?
Requirements Manage Plan
The project scope statement contains which of the following: (Choose 4)
A. Product Scope description
B. Risk
C. Assumptions Log
D. Deliverables
E. Stakeholder Register
F. Acceptance Criteria
G. Project Exclusions
A. Product Scope description
D. Deliverables
F. Acceptance Criteria
G. Project Exclusions
A _______ is a temporary endeavor undertaken to create a unique product, service, or result.
A. Portfolio
B. Program
C. Project
D. Phase
E. Scope
C. Project
A ________ is a group of related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually.
A. Portfolio
B. Program
C. Project
D. Phase
E. Scope
B. Program
A _______ is a collection of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.
A. Portfolio
B. Program
C. Project
D. Phase
E. Scope
A. Portfolio