PV - Planned Value
Def:
% of schedule (progress) that has passed x BAC
e.g. 25% of schedule passed x $250,000 = PV value of $62,500
BAC - Budget at Completion
Def:
Project Budget; the sum of all budgets established for the work to be performed.
EV - Earned Value
Def:
% of physical work completed x BAC
e.g. 40% work complete x $250,000 = EV value of $100,000
AC - Actual Cost
Def:
money spent as of status date
CV - Cost Variance
Def: amount of budget deficit or surplus at any given point in time CV = EV-AC "lesser is loser" positive number - under planned cost neutral number - on planned cost negative number - over planned cost
SV - Schedule Variance
Def: