Pressure Testing Flashcards

(22 cards)

1
Q

Pressure testing is accomplished using two different test mediums, liquid and gas. Which one is more dangerous?

A

Pneumatic testing since it has the potential to explode (measured in TNT).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is used to safely couple hydraulic hoses together?

A

Whip Check

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When using a hydrostatic pump, it is imperative that you check the electrical rating, why?

A

They come in different voltages. Use the rating plate for proper configurations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What components are required to preform a pressure test?

A

Hoses/fittings, pumps, compressors, pressurized gas cylinders, gauges/recorders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When preforming the test who or what needs to be consulted for the proper execution of the test?

A

Authority having jurisdiction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When increasing the test pressure, it should be brought up in stages why?

A

For safety purposes. Check for leaks and reduce damage that may occur as pressure increases.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When preforming a hydro test, as much air as possible needs to be vented. True or false?

A

True, allows you to reach test pressure and reduces chance of explosion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

6” pipe 500ft in length pressurized with air to 150lbs of pressure holds the equivalent of what force?

A

5lbs of TNT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the hazards of pressure testing?

A

Flying objects (flanges, valves, gauges, fittings….)
Flying shrapnel (shattered pipe or components from exploding)
Oxygen displacement from inert gas testing
Flooding in areas with electrical
Spills or leaks making ice in the cold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the purpose of a hydrostatic test on a piping assembly?

A

To ensure that the system can more than adequately carry its design pressure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the most popular method of testing piping systems?

A

Hydrostatic Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why is it necessary to install spill pans or other collection devices before a hydrostatic test?

A

To prevent environmental damage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What should be the maximum pressure rating for a hose used on the discharge of a pressure test pump?

A

Greater than the maximum rated discharge pressure of the pump.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What type of pressure gauge is usually used for pressure testing?

A

Bourdon Tube

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What components are used to make up a pressure test harness?

A

Union, pump shut off valve, pressure bleed valve, pressure gauge, recorder connection outlet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What should be done to prevent a universal coupling from coming apart while in use?

A

Install a safety pin across the mating halves of the connectors.

17
Q

What determines the maximum output pressure that a 100:1 ratio pneumatic diagram pump is capable of producing?

A

Input air pressure to the pump.

18
Q

What should the enclosure rating read on an electric motor used to drive a test pump in an area restricted for entry due to the possibility of an explosive or flammable atmosphere?

19
Q

What gas may be connected to a set of regulators having a CGA-540 connection?

20
Q

What type of gauge could be used on a line subject to moderate vibration during a hydrostatic test?

21
Q

What is the primary purpose of a pressure test?

A

To ensure a component assembly will not fracture under its maximum rated working pressure.

22
Q

What is the minimum time required for a hydrostatic leak test according to the ASME B31 codes?