PRINCE2 Foundation: Module 9 – Progress & Controls Flashcards

(Highlight Reports · End Stage Reports · Exception logic) (28 cards)

1
Q

What is the purpose of the Progress practice in PRINCE2?

A

To establish mechanisms to monitor compare and control actual progress against plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is progress control?

A

Monitoring actual performance against plans and taking corrective action when needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Highlight Report?

A

A time-driven report providing the Project Board with a summary of stage status.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who produces Highlight Reports?

A

The Project Manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who receives Highlight Reports?

A

The Project Board and any stakeholders specified by them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How often are Highlight Reports produced?

A

At intervals defined by the Project Board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an End Stage Report?

A

A report that provides information on stage performance and the status of the project at stage end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is an End Stage Report produced?

A

At the end of each management stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who uses the End Stage Report?

A

The Project Board to decide whether to authorize the next stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is an Exception?

A

A situation where tolerances are forecast to be exceeded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which THREE of the following are types of issues in PRINCE2?

Options:
A. Request for change
B. Off-specification
C. Problem or concern
D. Risk response

A

A. Request for change
B. Off-specification
C. Problem or concern

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an Exception Report?

A

A report produced when tolerances are forecast to be exceeded describing impact and options.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who produces an Exception Report?

A

The Project Manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Who decides on corrective action after an Exception Report?

A

The Project Board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is an Exception Plan?

A

A plan that replaces the current plan after approval to recover control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who approves an Exception Plan?

A

The Project Board.

17
Q

What is tolerance?

A

The permissible deviation from a plan without escalation.

18
Q

Which performance aspects can have tolerances?

A

Time cost scope quality risk benefits sustainability.

19
Q

What is management by exception?

A

Delegating authority within defined tolerances and escalating only when exceeded.

20
Q

Which PRINCE2 principle underpins progress control?

A

Manage by exception.

21
Q

What is a Checkpoint Report?

A

A time-driven or event-driven report from Team Manager to Project Manager.

22
Q

Who produces Checkpoint Reports?

A

The Team Manager.

23
Q

What is the purpose of a Checkpoint Report?

A

To report progress of work packages.

24
Q

Exam trap: Highlight Report vs End Stage Report – which is time-driven?

A

Highlight Report.

25
Exam trap: which report supports stage authorization?
End Stage Report.
26
Exam trap: who escalates when tolerances are forecast to be exceeded?
The Project Manager.
27
Exam trap: does actual breach or forecast trigger exception?
Forecast.
28
Exam trap: which plan replaces a Stage Plan after escalation?
Exception Plan.