The third phase of an architect’s regular services.
Contract documents phase
“The fee of the architect for design-build services on a guaranteed maximum cost aside
from his fee for regular design services.”
10%
“When the owner fails to implement the plans and documents for construction as
prepared by the architect, the architect is entitled to receive what percentage of his fee.”
85%
The minimum basic fee for industrial buildings with a project cost below 50 million pesos.
6%
“The release of 10% retention by the owner shall be done after how many months from
the date of final payment.”
3 months
“A price given by a contractor, sub-contractor, material supplier or vendor to furnish
materials, labor or both.”
Quotation
An offer to perform the work prescribed in a contract at a specified cost.
Bid
A list of instructions stipulating the manner on which bids are to be prepared.
Instruction to bidders
“How many days shall the Building Official issue a certificate of occupancy after final
inspection of the project.”
30 days
A rule that certain kinds of contracts are enforceable unless signed and in writing or unless there is a written memorandum of their terms signed by the party to be charged.
Statute of Frauds
The person receiving a possessory interest in buildings, property, etc., by lease.
Lessee
This type of compensation is only applied to non-creative work.
“Multiple of Direct
Personnel Expenses”
“This method of compensation is applied only to pre-design services, supervision work, and other works which the Architect may perform other than the regular and specialized
allied services.”
“Multiple of Direct
Personnel Expenses”
“This method of compensation is frequently used where there is continuing relationship
on a series of projects.”
Professional Fee Plus Expenses
How many sets of shop drawings for approval shall the contractor submit to the Architect?
3
“Who shall have the responsibility for establishing lot lines, boundary lines, easements,
and benchmarks?”
Owner
Professional fee for the Construction Manager.
1.5-3%
“At what interest rate per month should a client pay the architect should the former fail to
pay the latter beyond 30 days from receipt of billing?”
2%
What type of bond guarantees payment on all obligations arising from the contract?
Payment Bond
“If the Project Manager is hired by the owner, who shall have the responsibility of hiring
the Construction Manager?”
Project Manager
In the architect’s code of ethics, to whom does the architect has responsibility to seek opportunities for constructive service in civic and urban affairs?
Public / People
Additional information on contract documents issued to bidders before date of bidding.
Bid Bulletin
Instructions which may be issued prior to the bidding to supplement and/or modifydrawings, specifications, and/or general conditions of the contract.
Special Provisions
Includes labor or materials or both as equipment, transportation, or other facilities necessary to commence and complete the construction called for in the contract.
Work