What are the three major classifications of Project Delivery Methods?
What are the three linear stages of Traditional project delivery?
(- concept)
- Design
- Procurement (obtaining offers)
- Construction
What are the three prime players in Traditional project delivery?
How many contracts are there in Traditional project delivery, and who are they between?
Two contracts:
What are the advantages of Traditional project delivery?
What are the disadvantages of Traditional project delivery?
What are the two prime player in a Design-Build project delivery?
How many contracts does a Design Build project delivery have?
Just one - Owner & the Design Build entity
What are the advantages of Design Build project delivery?
What are the disadvantages of Design Build project delivery?
What is the Construction Management (CM) project delivery?
What are the advantages of CM project delivery?
What are the disadvantages of CM project delivery?
What are the two ways an Owner can engage a CM?
What are the four prime players in CM without Risk?
What are the three separate contracts in CM Without Risk?
What are the four prime player in CM at Risk?
What are the three separate contracts in CM at Risk?
typical projects
traditional
- not complicated, have been built before, well defined scope, min risk of changes, time/scheduale isnt significant factor, min political constraints
- road paving, single family house, warehouse, etc
design build
- highly technical where coordination between designers and builders essential
- projects that could benifit from fast tracking, eg start making money sooner
CM
- large complex projects
- projects for owners who dont have in house expertise to manage them
- commercial real estate developments
CM w/o risk
- big complex projects where owner wants to hire designer and builder directly but dosent have in house expertise to manage
CM at risk
- owners who dont intend to be involved day to day in design and construction process. owner pays cm to carry risk