How would you create a cashflow forecast?
If your construction budget was £2.5m and proposed construction
period was 25 weeks, would a forecast cashflow expenditure of
£100,000 per week be realistic?
What is the benefit of a cashflow forecast?
What would you include within a financial report?
What is the purpose of a financial report?
What are variations?
Alterations or modifications to the design, quality or quantity of the contract works or to the site access or working conditions.
Why might a variation arise?
What form must architect’s instructions take?
What about oral instructions?
Can the contractor object to a variation?
What can the architect do if the contractor does not comply with an instruction?
What 3 methods are there of obtaining a cost for variations under JCT forms of Contract?
What are the time periods for Schedule 2 quotations under JCT SBC?
o The architect should request via issue of an AI.
o The contractor has 7 days to notify that they will not provide one.
o If not, they have 21 days to provide the quotation.
o The architect then has 7 days to confirm in writing the acceptance or rejection.
o The acceptance is called the ‘confirmed acceptance’.
What costs does the schedule 2 quotation contain?
What costs is the contractor entitled to if the schedule 2 quotation is
rejected?
What are the valuation rules under JCT Forms of Contract?
There are three rules for measurable work:-
o If it is of a similar character, quantity and in the same conditions as existing work, then the bill
rates should be used.
o If it is of a similar character, but different quantity or conditions, the bill rates should be used as
a basis but a fair allowance should be made to take account of the difference.
o If it is not of a similar character, fair rates and prices should be used.
What about non-measurable work?
What is a star rate?
What are ‘fair rates and prices’?
What are dayworks?
What document should the prime cost be calculated in accordance
with?
This should be calculated in accordance with the ‘Definition of the Prime Cost of daywork carried out
under Building Contracts’ published by the RICS.
What information is necessary to be able to assess dayworks?
Can the QS alter hours which he considers to be excessive on a
dayworks sheet that is authorised by the architect?
What would you do if the contractor submitted 10 dayworks sheets to
you for payment?