What are activities in project management?
Jobs, tasks, events, steps, or sub-processes involved in completing a work package; they require time and resources.
What is ACWP (Actual Cost of Work Performed)?
The actual cost of each task at the current time.
What is an A&E contractor?
An organisation responsible for incorporating process and manufacturing technology requirements into the design of facilities.
What are assumptions in project management?
Statements taken for granted as truth.
What is a baseline?
A snapshot in time of a project plan against which progress can be measured.
What is bottom-up cost estimating?
Making detailed estimates for every activity in the WBS and summing them for a total project cost estimate.
What is a budget?
A planned allocation of resources.
What are B&R codes?
Codes linked to the WBS, assigned to cost data for monitoring, reporting, and forecasting.
What is BAC (Budget at Completion)?
The planned cost for a task.
What is BCWS (Budgeted Cost of Work Scheduled)?
Planned percentage complete (based on dates) × planned cost; also called Planned Value.
What is BCWP (Budgeted Cost of Work Performed)?
Percentage completed × planned cost at current time; also called Earned Value.
What is a case structure?
Breakdown of the project budget into case, sub-case, and sub-sub-case levels.
What is a charter?
See project team charter.
What is a chunk chart?
A prioritised list of projected work areas for a case number and financial year in a programme’s sector data document.
What is concurrent engineering?
A systematic approach to integrated, simultaneous product and process design, including manufacture, test, and support.
What are contingencies?
Specific provisions for unforeseeable cost elements within project scope.
What are constraints?
Applicable restrictions that affect project scope.
What is a CBS (Cost Breakdown Structure)?
A hierarchical system linking project costs to the WBS or OBS.
What is cost estimating?
Assembling and predicting the costs of a project.
What is cost management?
The function of maintaining financial control through evaluating, estimating, budgeting, monitoring, forecasting, and reporting costs.
What is a cost plan?
Resource needs by month/year, including labour, charges, and assessments for each sub-case.
What is CV (Cost Variance)?
The difference between BCWP (earned value) and ACWP (actual cost).
What are critical activities?
Tasks whose duration increases would likely affect the project’s overall duration.
What is the critical path?
The longest sequence of interdependent tasks determining project duration; any delay delays the project.