What is NRM2?
provides a set of detailed measurement rules for the preparation of bills of quantities or schedules of rates for the purpose of obtaining a tender price. It also deals with the quantification of non-measurable work items, contractor designed works and risks. Guidance is also provided on the content, structure and format of bills of quantities, as well as the benefits and uses of bills of quantities.
What is the BCIS?
The Building Cost Information Service (BCIS) online database contains elemental cost analyses for over 17,500 projects across the UK - information you will find indispensable when preparing cost plans, providing early cost advice to clients and benchmarking costs.
What is a GIFA?
Gross internal floor area
What is a benchmark?
Benchmarking, the process of comparing projected or actual project cost and performance information against information from similar projects, is key to the development of the plan.
How would did you measure the fencing remeasure contract?
I reviewed NRM2 for the correct measurement unit which was metres
Stating the required height
Reviewed the contract for the applicable measure
Measured off drawings
Check measure on site
Issue remeasurement to contractor
What instance would you use daywork to price an item of works?
The method of valuing work on the basis of the time
spent by the contractor’s team, the materials used and
the plant employed
When the material nature of the works is unquantifiable and or the is no suitable rate for the works
How did you remeasure the remaining quatity of joinery works following insolvency of the contractor?
Scope of works reviewed
Schedule of works chekced on site what was still to be carried out
Remeasured relevant items and produced a new schedule of works
How did you remeasure the retaining walls on Claremount Road?
Checked NRM for suitable unit
m2 - thickness stated
carried out on site measure documenting thickness and measure supporting photos
How did you measure materials on site for the valuation?
Checked require units of materials
Performed a count check
Recorded on external valuation or checked subbie applications
How did you measure the mastic pointing for the BoQ?
NRM2 measured in metres
issued measure to subbie
What does the government code of measuring practice state?
What is IPMS?
Updated in 15/01/2023
- Made up of multiple bodies across the world including RICS and RIBA
- Sets rules for measuring GEFA and GIFA
- Applicable to all types of buildings and purposes, inc analysis and benchmarking, construction rates and ratios, property development, financing and management
- Seeks to avoid confusion with existing terms
- 3 different groupings- IPMS 1 and 2 for external and internal measurements for whole / part of building
- IPMS 3 - ext and int measurements for excluding occupation (NIA)
- IPMS 4 - internal measurements required for selected areas, inc int walls and columns
Why were the New Rules of Measurement introduced?
If producing estimates and cost plans, which measurement rules represent industry best practice for capital building and building maintenance works in the UK?
Why should you use the NRM?
Can you name the 3 documents in the NRM suite?
Why did NRM update?
Updated in 2021 to align with IPMS, ICMS and RIBA Plan of Work 2020.
Can you provide a brief overview of NRM1?
How does NRM define the ‘cost limit’ for the project?
How does NRM define the ‘base cost estimate’ for the project?
Can you provide a brief overview of NRM2?
Key headings for contractor preliminaries identified in NRM 2?
Types of BoQ under NRM2?
Firm
- Reliability of tender price increases in relation of accuracy of quants provided. If no design changes, firm BoQ at tender stage = final cost
Approximate
- Not enough detail to prepare firm, decided by client that time/cost to produce firm one not warranted
- No lump sum price provided, but tender price totals
- Qty’s subject to remeasurement on completion by QS / cost manager
What items would you measure in association with structural steelwork under NRM 2?