RC 1 Flashcards

(41 cards)

1
Q

What is the main purpose of clearing and grubbing?

A. To level the site for drainage
B. To remove existing roads
C. To remove vegetation and obstruction
D. To excavate the roadway

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the minimum depth for slumo and root removal

A. 200 mm
B. 300 mm
C. 500 mm
D. 1000 mm

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How is clearing and grubbing mesured?

A. Cu.m
B. Sq.m
C. L.m
D. Hectare

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Under Item 101, which of the following is typically NOT removed?

A. Old pavements
B. Buildings
C. Guardrails
D. Embankment Fills

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What happens o salvageable materials during removal operations?

A. Discarded
B. Buried Onsite
C. Reused and stored as directed
D. Auctioned

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is included in the payment for removal operations?

A. Demolition Only
B. Transportation Only
C. Removl and proper disposal
D. Equipment rental only

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the standard free-haul distance for excavation?

A. 100 m
B. 300 m
C. 500 m
D. 600 m

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following is NOT a type of excavation in Item 102?

A. Roadway Excavation
B. Borrow Excavation
C. Selected Borrow for Embankment
D. Concrete Excavation

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is excavation work measured?

A. By weight
B. By sq.m
C. In-place volume
D. Original ground volume (cu.m)

A

D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Structure excavation is used primarily for

A. Canal cleaning
B. Drainage maintenance
C. Foundations for brides and culverts
D. Traffic signs installation

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Measurement of structure excavation includes

A. Surface area
B. Total road length
C. Design volume plus working space
D. Design depth only

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Maximum uncomoacted thickness of embank,ent layer is

A. 150 mm
B. 200 mm
C. 300 mm
D. 350 mm

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the required compaction for embankment material?

A. 90%
B. 93%
C. 95% of MDD
D. 98%

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What test is typically used to determine MDD for embankment compation

A. AASHTO T97
B. AASHTO T89
C. AASHTO T180 or T99
D. AASTO T11

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What must be completed before subgrade preparation begins

A. Traffic lights
B. Drainage structures and culvert backfilling
C. Asphalt paving
D. Fence installation

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the maximum surface irregularity allowed in subgrade

A. 10 mm
B.20 mm
C. 30 mm
D. 50 mm

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Minimum depth of compaction below subgrade level is

A. 100 mm
B. 120 mm
C. 150 mm
D. 200 mm

18
Q

What is the typical area of a control strip

A. 100 sq.m
B. 200 sq.m
C. 335 sq.m
D. 500 sq.m

19
Q

What is the required target density for control strips

A. 95%
B. 97%
C. 98% of lab-compacted density
D. 100%

20
Q

When is a new control strip required?

A. Change in material
B. Every 10 days
C. Engineer’s instruction
D. All of the above

21
Q

What is “overhaul”

A. Excavation below water table
B. Hauling beyond the free-haul distance
C. Rehandling unsuitable materials
D. Doucble compaction of borrow

22
Q

What is the unit of payment for overhaul

A. Cu.m
B. L.m
C. q.m
D. Cu.m-km

23
Q

If the contractor uses a longer haul rout not approved by the Engr, what is the payment basis?

A. Actual longer distance
B. Roun trip
C. Shortest feasible route designated by the Engr
D. No payment

24
Q

Before beginning earthwork operations on a new road alignment, the ME observes that there are several large trees, old concrete fence posts, and thick vegetation. What should be the FIRST step in compliance with DPWH Item 100?

A. Start excavation work alongside the vegetated area
B. Submit a tree-cutting permit and start grubbing the area
C. Clear and grub the entire roadway width, remove obstruction, and dispose properly
D. Cut only the smallvegetation and return for the rest of the subgrade work

25
An old culvert pipe lies within the new pavement area. The contract includes Item 101. The Engr orders its removal and reuse if salvagebale. How should this be handled? A. Remove and discard immediately regardless of co ndition B. Demolish and disposed at the borrow pit C. Remove carefully, stockpile slvageable parts, and resure or store as directed D. Abandon in place and cover with embankment
C
26
During excavation, the contractor hauls common material 900 m away to the designated embankment site. What portion is overhaul? A. Full 900m B. First 300m C. 300m D. 900m minus the 600m free haul
D
27
28
The embankment layers are being places at 300mm uncompacted thickness. Compaction tests show non-compliance. What action is most appropriate? A. Continue as long as progress is fast B. Accept the work and place the enxt layer C. Remove the layer and compact in two lifts not exceeding 200mm each D. Add water and recompact at 300mm
C
29
You inspect a road section where pavement construction has started but culverts and drains are not yet completed. Is this allowed? A. Yes if equipment is available B. No prior works must be completed and apprpved C. Yes if weather is good D. Yes provided embankment is stable
B
30
Before full-scale embankment compactiom. the Engr instructs the Contractor to construct a 335sq.m test area. The average density obtained is 96% of the laboratory value. What should be done? A. Proceed with compaction using 96% B. Accept control strip and begin full compaction C. Construct another control strip until 98% is achieved D. Increase the lift thickness for better ersults
C
31
The contractor decides to use a longer but smoother route fo hauling borrow material from a pit 800m away. The Engr had designated a shorter 650m route. For emasurement of overhaul, which distance should be sued? A. 700m B. 600m C. 650m D. Difference between 800 and 600
C
32
During quality control inspection of a road project, your compaction tests at a 150mm thk embankment layer shows 93% compaction. The required is 95% MDD as per AASHTO T99. Moisture content is within acceptable limits. A. Apply a proof roller and proceed with the enxt layer B. Accept the reslt since it is close to 95% C. Require additional compaction until 95 is achieved D. Apply lime stabilization to improve compaction
C
33
Subgrade inspection reveals elevation discrepancies +22mm in one section and -35mm in another A. Accept both since surface irregularit is within 30mm B. Only correct the -35mm C. Correct both to meet at 20mm level and 30mm irregulatiry tolerance D. Increase thickness of base course to compensate
C
34
Contrl strip for asphalt base yields 97.2% compaction compared to Marshall lab specimen. Equipment used is different from that intended for actual construction. A. Accept the control strip and beign full paving B. Repeat control strip using the actual construction equipment C. Accept if within +-3% of the lab result D. Use rolling pattern developed in the current ontrol strip
B
35
During excavation for a footing, water seeps from the side, saturating the bottom. Contractor proposes to proceed by placing concrete. As ME, what should you advise? A. Allow concreting with added cement for strength B. Dewater and stabilize before pouring concrete C. Proceed only if water is clear D. Apply a binding layer and pour concrete
B
36
A 2000 cu.m volume of suitable embankment material is transported 1.2km. The contract provides for a 600m free haul. What is the total qty in cu.m-km eligible for overhaul payment? A. 2400 B. 1200 C. 1000 D. 600
B
37
A contractor proposes to plac 300 mm loose thickness layers to speed up embankment work, with single-pass compaction using a 10-ton roller. As ME, how do you respond? A. Approve the plan if compaction tests pass B. Reject the method and require max 200 mm loose thickness C. Allow for weathered soil types only D. Accept if supervised by Engineer-in-Charge
B
38
You are retrofitting a concrete road by overlaying asphalt. The existing PCC pavement has not been broken into smaller slabs. According to Item 105, what step must be performed before proceeding? A. Seal cracks with epoxy B. Scarfiy the slab surface and clean C. Break the PCC into <= 500mm slab and comapct D. Apply bituminous tack coat
C
39
A 5.5-ton vibratory roller is used for the control strip of base course. Upon review, it is found to be under 6 tons. What is the most correct action based on specs? A. Approve use of the roller as-is B. Require additional passes to make up for size C. Reject and require 6-ton minimum vibratory roller D. Require proof rolling test
C
40
After excavation, a portion of the cut section is left open and unprotected for several days. Rainfall causes erosion and slope failure. What specificaton or construction management issue is primarily violated? A. No slope protection measures implemented B. Lack of engr's approval C. No rebard cages installed D. Compaction was not performed
A
41
The contractor wants to use rock materials larger than 150mm in diameter at the base of an embankment section. What is the correct procedure under DPWH specifications? A. Mix with soil to stabilize B. Allow only in the top 1 meter C. Place in layers, fill voids with finer material, and compact D. Reject rock emabnkment below 200 mm
C