What is the main purpose of clearing and grubbing?
A. To level the site for drainage
B. To remove existing roads
C. To remove vegetation and obstruction
D. To excavate the roadway
C
What is the minimum depth for slumo and root removal
A. 200 mm
B. 300 mm
C. 500 mm
D. 1000 mm
C
How is clearing and grubbing mesured?
A. Cu.m
B. Sq.m
C. L.m
D. Hectare
D
Under Item 101, which of the following is typically NOT removed?
A. Old pavements
B. Buildings
C. Guardrails
D. Embankment Fills
D
What happens o salvageable materials during removal operations?
A. Discarded
B. Buried Onsite
C. Reused and stored as directed
D. Auctioned
C
What is included in the payment for removal operations?
A. Demolition Only
B. Transportation Only
C. Removl and proper disposal
D. Equipment rental only
C
What is the standard free-haul distance for excavation?
A. 100 m
B. 300 m
C. 500 m
D. 600 m
D
Which of the following is NOT a type of excavation in Item 102?
A. Roadway Excavation
B. Borrow Excavation
C. Selected Borrow for Embankment
D. Concrete Excavation
D
How is excavation work measured?
A. By weight
B. By sq.m
C. In-place volume
D. Original ground volume (cu.m)
D
Structure excavation is used primarily for
A. Canal cleaning
B. Drainage maintenance
C. Foundations for brides and culverts
D. Traffic signs installation
C
Measurement of structure excavation includes
A. Surface area
B. Total road length
C. Design volume plus working space
D. Design depth only
C
Maximum uncomoacted thickness of embank,ent layer is
A. 150 mm
B. 200 mm
C. 300 mm
D. 350 mm
B
What is the required compaction for embankment material?
A. 90%
B. 93%
C. 95% of MDD
D. 98%
C
What test is typically used to determine MDD for embankment compation
A. AASHTO T97
B. AASHTO T89
C. AASHTO T180 or T99
D. AASTO T11
C
What must be completed before subgrade preparation begins
A. Traffic lights
B. Drainage structures and culvert backfilling
C. Asphalt paving
D. Fence installation
B
What is the maximum surface irregularity allowed in subgrade
A. 10 mm
B.20 mm
C. 30 mm
D. 50 mm
C
Minimum depth of compaction below subgrade level is
A. 100 mm
B. 120 mm
C. 150 mm
D. 200 mm
C
What is the typical area of a control strip
A. 100 sq.m
B. 200 sq.m
C. 335 sq.m
D. 500 sq.m
C
What is the required target density for control strips
A. 95%
B. 97%
C. 98% of lab-compacted density
D. 100%
C
When is a new control strip required?
A. Change in material
B. Every 10 days
C. Engineer’s instruction
D. All of the above
D
What is “overhaul”
A. Excavation below water table
B. Hauling beyond the free-haul distance
C. Rehandling unsuitable materials
D. Doucble compaction of borrow
B
What is the unit of payment for overhaul
A. Cu.m
B. L.m
C. q.m
D. Cu.m-km
D
If the contractor uses a longer haul rout not approved by the Engr, what is the payment basis?
A. Actual longer distance
B. Roun trip
C. Shortest feasible route designated by the Engr
D. No payment
C
Before beginning earthwork operations on a new road alignment, the ME observes that there are several large trees, old concrete fence posts, and thick vegetation. What should be the FIRST step in compliance with DPWH Item 100?
A. Start excavation work alongside the vegetated area
B. Submit a tree-cutting permit and start grubbing the area
C. Clear and grub the entire roadway width, remove obstruction, and dispose properly
D. Cut only the smallvegetation and return for the rest of the subgrade work
C