Plan Schedule Management - Inputs/T&T/Outputs
Inputs .1 Project charter .2 Project management plan .3 Enterprise environmental factors .4 Organizational process assets
Tools & Techniques
.1 Expert judgment
.2 Data analysis
.3 Meetings
Outputs
.1 Schedule management plan
Define Activities - Inputs/T&T/Outputs
Inputs
.1 Project management plan
.2 Enterprise environmental factors
.3 Organizational process assets
Tools & Techniques .1 Expert judgment .2 Decomposition .3 Rolling wave planning .4 Meetings
Outputs .1 Activity list .2 Activity attributes .3 Milestone list .4 Change requests .5 Project management plan updates
Sequence Activities - Inputs/T&T/Outputs
Inputs .1 Project management plan .2 Project documents .3 Enterprise environmental factors .4 Organizational process assets
Tools & Techniques .1 Precedence diagramming method .2 Dependency determination and integration .3 Leads and lags .4 Project management information system
Outputs
.1 Project schedule network diagrams
.2 Project documents updates
Estimate Activity Durations - Inputs/T&T/Outputs
Inputs .1 Project management plan .2 Project documents .3 Enterprise environmental factors .4 Organizational process assets
Tools & Techniques .1 Expert judgment .2 Analogous estimating .3 Parametric estimating .4 Three-point estimating .5 Bottom-up estimating .6 Data analysis .7 Decision making .8 Meetings
Outputs
.1 Duration estimates
.2 Basis of estimates
.3 Project documents updates
Develop Schedule - Inputs/T&T/Outputs
Inputs .1 Project management plan .2 Project documents .3 Agreements .4 Enterprise environmental factors .5 Organizational process assets
Tools & Techniques .1 Schedule network analysis .2 Critical path method .3 Resource optimization .4 Data analysis .5 Leads and lags .6 Schedule compression .7 Project management information system .8 Agile release planning
Outputs .1 Schedule baseline .2 Project schedule .3 Schedule data .4 Project calendars .5 Change requests .6 Project management plan updates .7 Project documents updates
Control Schedule - Inputs/T&T/Outputs
Inputs .1 Project management plan .2 Project documents .3 Work performance data .4 Organizational process assets
Tools & Techniques .1 Data analysis .2 Critical path method .3 Project management information system .4 Resource optimization .5 Leads and lags .6 Schedule compression
Outputs .1 Work performance information .2 Schedule forecasts .3 Change requests .4 Project management plan updates .5 Project documents updates