Inputs: Plan Schedule Management
Outputs: Plan Schedule Management
Schedule Management Plan
Schedule Management Plan
Outlines how the project carry out each process in the knowledge area, as well as how to measure the schedue and make corrections for variances.
Components of Schedule Management Plan
Inputs: Define Activities
Outputs: Define Activities
Schedule Data
used to show what data were used to create the schedule, including constraints and assumptions made to create the schedule
Inputs: Sequence Activities
Outputs: Sequence Activities
Activity Attributes
More detailed information about each individual activity.
Can include resources needed, location of the activity, cost, assumptions, constraints, leads and lags, and relationships to other activities
Precedence Diagramming Method (PDM)
used to create network diagram.
nodes (boxes) represent activities, arrows represent dependencies. numbers on nodes show activity duration estimates
Types of Dependencies
Mandatory
Discretionary
External
Internal
Keys to Increasing Estimate Accuracy
Note: no padding of estimates under PMI.
Inputs: Estimate Activity Durations
Outputs: Estimate Activity Durations
PM’s role in estimating
Analagous Estimating
aka top-down estimating
aggregate estimate of project costs, using histoical data from past, similar projects.
Parametric Estimating
Creating a mathematical equation to determine relationships between historical data & other variables. Includes historical information review, regression analysis, learning curves.
3-point estimates
Triangular estimate
Beta distribution
Bottom-up Estimation
estimates each activity (or work packages, if activities not available), then aggregates to control accounts and overall project estimate
Types of Reserves
Contingency Reserves (known unknowns)
Management Reserves (unknown unknowns)
Schedule Compression Options
Fast Track (do activities on critical path in parallel instead of sequence (increases risk)
Crash (more resources, increases costs, sometimes increses risk)
Reduce Scope (may save cost, time, resources)
Cut Quality (may save cost, time, resources, but increase risk)
Critical Chain Method
places project buffer at end of project instead of throughout project.
build aggressive schedule, then at end of schedule add large buffer
Resource Optimization Techniques