Define the parts of a node in a “on Node (AON) network”
1-2-3 5 7-8-9 1: Earliest star time 2: Duration 3: Earliest finish time 5 task identifier 7: Latest start time 8: Total float 9: Latest finish time Free Float
What is total floats?
Total float is the amount of time an activity can be delayed without affecting the project completion date. It is the difference between LST- EST or LFT-EST
What is Free floats?
Free floats is amount fo time an activity can be delayed without affecting the start date of any of its successors. Free Float= EST of earliest successor - EFT
What are the advantages of a Gantt Chart?
What are the limitations of a Gantt Chart?