To reduce the potential for the Turbine to roll off the Turning Gear, shell warming should begin as close to 60 psig Reactor pressure as possible.
OP-21 P&L-13
Remove pumps from service to prevent turbine from rolling off the turning gear. Should not exceed 50RPM. May shutdown 6 of 8 lift pumps, must maintain lift pumps for bearings 9 and 10 (P6G/H - Generator Bearings) running.
OP-21 page 22
~CAUTION~
If water induction is evident while Turbine is accelerating, Turbine must immediately be tripped and placed on turning gear to prevent or minimize damage to the Main Turbine.
IF any of the following occur WHILE bringing the Turbine to speed, THEN immediately trip Turbine per N2 SOP 21, Turbine Trip [C4].
• Signs of water induction into Main Turbine
~NOTE~
Turbine Bearing Vibration indications shall be confirmed using adjacent bearing(s) indication, bearing temperature indication, (etc. 2CEC-PNL842 and computer points indications) or local investigation.
• Any confirmed Turbine Bearing Vibration greater than 9 mils with greater than 3 mils/minute rate of change
• IF any confirmed Bearing Vibration is greater than or equal to 12 mils WITH two consecutive readings on recorder 2TMI NBR134.
• Any confirmed Turbine Bearing Vibration greater than or equal to 10 mils for 15 minutes
• Smoke OR fire associated with Main Turbine OR Generator/Exciter
• Other unusual conditions as directed by SM/CRS
OP-21 E.5.15
To reduce metal thermal stresses and potential rubbing due to uneven component expansions during activities such as shell warming and changes in load, High Pressure Turbine Shell Temperature changes should have a target rate of less than 125°F/Hr and are limited to a rate of 150°F/Hr, or about 40°F every 15 minutes.
P&L 22
~NOTE~
Chest warming is required if Control Valve Inner Temperature is less than 500°F (Computer Point TMITA02 or Recorder 2TMI TR137/ZDR135, Point 6).
OP-21 E.4
OP-21 E.5.3.2 High Pressure Turbine Shell Inner Temperature is greater than 250°F.
~NOTE~
• Personnel performing this procedure should be familiar with expected Turbine startup vibration. Vibration should peak during Rotor Critical Speeds (about 900 to 1300 rpm).
• No automatic turbine trip exists on high vibration.
OP-21 above E.5.4
Single notch control rod movement shall be performed from notch positions 00 to 36: [C19]
− At the direction of the Reactor Engineer if Estimated Critical Range (ECR) is PRIOR to Rod Worth Minimizer (RWM) rod group 3.
− IF 3 count rate doublings are approached on at least 2 SRMs PRIOR to RWM rod group 3.
− Starting with RWM rod group 3 UNTIL criticality is achieved.
− For RWM rod groups 3 AND 4 AFTER the reactor is critical, unless otherwise directed by Reactor Engineer.
OP-101A att 1.D.1
a. 00-04
b. 04-08
c. 08-12
d. 12-16
e. 16-24
f. 24-48
Position Worth
00-04 Low 04-08 High 08-12 Highest 12-16 High 16-24 Low 24-48 Minimal
OP-101A att 1.D.2
The General Supervisor Operations (or designee) shall identify those systems for which a system lineup is NOT required. This decision will be based on the extent of work performed on the system during the outage and the safety significance of the system.
OP-101A Att 3
Commence Off Gas recombiner heat trace warming per N2 OP 42 at least three days PRIOR to planned start up of Off Gas System.
OP-101A Attachment 3.D.5
Can NOT exceed 150psig before performing N2 OSP ICS Q@002 for SR3.5.3.4 (OP-101A E.2.37)
~NOTE~
When reactor pressure exceeds 935 psig with 1 turbine bypass valve full open and N2 OSP ICS Q@002 is required, a 12 hour clock for test performance will start. (SR 3.5.3.3)
OP-101A above E.3.18
~NOTE~
Eight demineralizers are required for 100% power. Nine demineralizers are preferred for additional operational margin.
Place Condensate Demineralizers in service as required in order recommended by Chemistry AND maintain individual demineralizer flows between 2000 AND 3300 gpm (3500gpm MAX) AND a system delta P less than or equal to 55 psid (60 psid maximum).
OP-101A E.5.4
Within 24 hours AFTER exceeding 23% of RATED THERMAL POWER, perform N2 OSP LOG D001, Daily Checks, Jet Pump Operability. (TS 3.4.3)
OP-101A E.5.9.3
~Caution~
It is possible, following RCS pump downshift, that steam flow indication can drop low enough to cause difficulty with 3-element feedwater level control. Should this occur, G.1.26.1, “Placing feedwater level control in single element,” should be performed without delay following the downshift.
N2-OP-101C Section G (pg. 18 of 92)
HDL Pumps provide 1/3 of total condensate flow – may have trouble maintaining RPV Level at 100% without challenging the Condensate System with Runout.
Additionally iaw P&L 17 of OP-8, long term operation on the high level dumps could cause condenser damage.
~CAUTION~
Seat leakage problems have been experienced with the 2FWS LV10s in the past. After valve repair, the leakage is eradicated or minimized but will degrade as the valve wears. If leakage past the LV10s has been observed to be degrading, caution needs to be observed when opening 2FWS MOV47A, B, C valves. Leakage past the LV10s can cause level and associated power excursions, particularly at lower reactor pressures. [C3]
IF 2FWS LV10A(B) leak by is suspected,
THEN make 2FWS MOV47A(B) throttleable per H.3.0 of this procedure.
OP-3 E.3.43.1
IF SRV opening is required to control rising Reactor Pressure, THEN exit this procedure AND enter N2 SOP 101C, Reactor Scram.
OP-101C G.4.19
WHEN Reactor pressure reaches approximately 925 psig, THEN perform the following:
IPTE portion of plant startup is now complete. Log completion in Control Room Log.
OP-101A E.2.49
Verify Main Steam Line Hi-Hi Rad Alarms are Clear
SOP-101C Discussion 5.8
Residual Heat Removal System removed from Shutdown Cooling mode AND operable for LPCI mode per N2 OP 31, Residual Heat Removal System
OP-101A E.1.16.1
All ECCS Must be Operable prior to Mode 2 Entry iaw Tech Spec
Additionally, you do not want anything other than Rods affecting reactivity during startup.
To prevent crossflow from the primary containment to the reactor building when using the 20” line to GTS, (2GTS*AOV101), the following plant parameters shall be maintained:
i. Primary containment pressure less than 0.41 psig.
ii. Reactor building pressure shall not be more negative than −1.0” water.
iii. Purge flow (air/nitrogen) shall be maintained less than GTS out flow.
OP-61A P&L 7