______ is the practice of reviewing contract documents, including the prints and specifications, to determine quantities of material to be included in the bid.
Takeoff
The takeoff for excavation is commonly calculated in _______ _______.
cubic yards
Calculating the volume of material to be excavated from a site is accomplished using the ________ or ______ ______ _____ method.
cross-section
average end area