You Should Understand
Task Item No. 5-2: Develop Preliminary Project Descriptions, outline specifications, and project manuals.
Reading List
Task Item No. 5-2: Develop Preliminary Project Descriptions, outline specifications, and project manuals.
CSPG 1.9.1, 1.10, 4.2.2.1 through 4.2.2.2, 8.4, and 11.1 through 11.3
Refer to Task Item 5-1
1.9 Preparing the Specifications
Specification sections may either befollowing the CSI principles described in this chapter or be created by. Although text for specification sections may be derived from several sources, the use of master guide specifications is most common. Preparing specifications from information that is not in a usable specification format should follow the principles and techniques detailed in this chapter.
1.9 Preparing the Specifications
Specification sections may either be written from scratch following the CSI principles described in this chapter or be created by editing available master guide specifications. Although text for specification sections may be derived from several sources, the use of master guide specifications is most common. Preparing specifications from information that is not in a usable specification format should follow the principles and techniques detailed in this chapter.
1.9.1 Writing/Editing Preparation
The specifier should review for the work covered in each section. and prepared during the early design phases may be helpful. It is also important to thoroughly review the drawings, details of construction, and schedules. Local conditions and governing codes must also be considered, as both proprietary and master guide specifications may not address local project conditions or may contain references that do not apply. Prepare a preliminary table of contents for the project manual by identifying the specification sections from Master- Format® that will be needed to cover the extent of the project. As a general rule, sections of Divisions 02 through 49 should be written before completing Division 01 sections.
1.9.1 Writing/Editing Preparation
The specifier should review project requirements for the work covered in each section. Preliminary project descriptions and outline specifications prepared during the early design phases may be helpful. It is also important to thoroughly review the drawings, details of construction, and schedules. Local conditions and governing codes must also be considered, as both proprietary and master guide specifications may not address local project conditions or may contain references that do not apply. Prepare a preliminary table of contents for the project manual by identifying the specification sections from Master- Format® that will be needed to cover the extent of the project. As a general rule, sections of Divisions 02 through 49 should be written before completing Division 01 sections.
1.10 Producing a Project Manual
The project manual preparation should begin early in the construction documents phase. The following tasks should be performed, generally in this order:
1.10 Producing a Project Manual
The project manual preparation should begin early in the construction documents phase. The following tasks should be performed, generally in this order:
8.4 Responsibility for Coordination
One person should be the coordinator and should have the responsibility for reviewing consistency between theand the. In preparing drawings and specifications, the specifier and A/E should work together, keeping in mind the difficulties faced by estimators, bidders, contractors, inspectors, and product representatives.
A preliminary project description or outline specification should be developed as a, and additional conferences should be held as the design progresses. Specification preparation should proceed, and coordination should become a continuous process from the beginning of the project.
8.4 Responsibility for Coordination
One person should be the coordinator and should have the responsibility for reviewing consistency between the drawings and the specifications. In preparing drawings and specifications, the specifier and A/E should work together, keeping in mind the difficulties faced by estimators, bidders, contractors, inspectors, and product representatives.
A preliminary project description or outline specification should be developed as a Checklist, and additional conferences should be held as the design progresses. Specification preparation should proceed concurrently with design, and coordination should become a continuous process from the beginning of the project.
11.1 Introduction to Shortform Specifications
Some projects of limited scope and extent may need less detailed descriptions than those provided by a typical full length specification. Similarly, for projects with a negotiated contract or design-build delivery method, a specification with reduced detail may be appropriate. In these cases, an architect/engineer (A/E) may choose, or an owner may request, to use a shortform specification.
11.2 Concept of Shortform Specifications
The purpose of shortform specifications is to provide a concise set of construction specifications commensurate with theof a project and to reduce the level of detail where it is appropriate. Correctly developed, the resulting shortform specification will be concise without the omission of critical information.
11.2 Concept of Shortform Specifications
The purpose of shortform specifications is to provide a concise set of construction specifications commensurate with the size and extent of a project and to reduce the level of detail where it is appropriate. Correctly developed, the resulting shortform specification will be concise without the omission of critical information.