What is the difference between express time and NO express time?
When can a contract be terminated for delay?
If time is CLEARLY a condition –> aggrieved party can terminate contract at ANY time after due date b/c ‘time is of the essence’
When is time considered ‘of the essence?’
What about Sales of Goods Contracts for time?
What if time is NOT of the essence, when will delay constitute as repudiation?
If general test of repudiation is satisfied –> delay is SO long or is in circumstances that is evinces an intention not to be bound by the contract
- After notice procedure: the breaching party is given notice to perform within a reasonable time but fails to do so
When can notice be given?
If express term –> as soon as delay occurs
If non-express term –> within reasonable timeframe
What must be contained in a ‘Notice’ for it to be valid?
What if a Notice is given at the right time with the right content?
–> Failure to comply MAY lead to repudiation