Nominal Pipe Size
True
strong, heavy
True
schedule
inside
outside
thicker
Nominal Pipe Size (NPS) & schedule number (SCH)
12
greater
more
Using the ANSI Pipe Schedule, answer the questions below.
11. For the following pipe sizes, state the pipe outside diameter:
a. 2-inch ______
b. 6-inch ______
c. 12- inch _____
d. 16-inch _____
a. 2-inch 2.375”
b. 6-inch 6.625”
c. 12- inch 12.750”
d. 16-inch16.000”
Using the ANSI Pipe Schedule, answer the questions below.
12. For the following pipe sizes, calculate the pipe inside diameter:
a. 2-inch XH _______
b. 8-inch Schedule 40 _______
c. 12-inch Schedule 40 ______
d. 20-inch Schedule 80 ______
a. 2-inch XH 2.375 - 2 x .218 = 1.939”
b. 8-inch Schedule 40 8.625 - 2 x .322 = 7.981”
c. 12-inch Schedule 40 12.750 - 2 x .406 = 11.938”
d. 20-inch Schedule 80 20.000 - 2 x 1.031 = 17.938”
Using the ANSI Pipe Schedule, answer the questions below.
13. What is the weight per foot in pounds of the following pipe sizes:
a. 2-inch XH _____
b. 10-inch Schedule 40 ______
c. 20-inch Schedule 40 ______
d. 30 -inch XH _________
a. 2-inch XH 5.03
b. 10-inch Schedule 40 40.52
c. 20-inch Schedule 40 123.23
d. 30 -inch XH 157.68
Brass
Carbon Steel
Stainless Steel
Cast Iron
Special Alloys
Ductile Iron
Casting Method and Forging Method
Mold or core preparation, Metal melting, Pouring molten metal into the mold, Solidifying the metal, Removing the cast component from the mold, Finishing and polishing the component
Cutting and forging the metal, Trimming excess material, Sandblasting to smooth and clean surfaces, Machining to refine shape and dimensions, Surface treatment to enhance component properties