what is the purpose of the progress theme
what are the 2 types of controls throughout a project to assess the progress
how do the project board work by “management by exception”
because they are kept informed about the project through highlight reports and only have progress meetings if there will be deviation from the tolerance levels
what are the main controls for the project board to assess progress
what are the main controls for the project manager to assess progress
How does Prince2 allow the project to progress smoothly without frequent and unnecessary communication between the different levels within the project team
by defining tolerances for time, cost, quality, risk, benefit and scope.
who sets the overall requirements and tolerance levels for the project
Corporate or Programme management
*Note: if the project is likely to exceed the agreed project tolerances, the project board must inform Corporate or Programme management *
who allocates the tolerances for each management stage
The project board do this and inform the project manager of what the tolerances are
Note: The Project Board can review progress and decide whether to continue, change or stop the project
how does the project manager inform the project board of deviations that exceed tolerances
They inform the project board through exception reports
what does a team manager have control of
has control of a work package, within the work package tolerances agreed with the Project Manager.
If tolerances are likely to be exceeded, the team manager will raise it as an issue to the project manager
what is the Prince2 minimum to assess the progress of a project
what are the 3 ways control in a project is provided by to monitor progress