How do you make a Network Diagram
Estimation table. What is the formula for estimating time?
( P + O + 4M ) / 6
What are the two major methods of time estimating?
Bottom-up (the team hammers out activity time)
Top-Down (Senior management estimates the total project time and allocates it to the project.Schedules of past projects may be used to estimate time)
Gathering Resources: Name a few items that you will want to gather before starting the schedule process?
Gathering Resources
•Calendars of people working on ht project. Include outsourced vendors. Make note of when they are very busy or unavailable
• Vacation time for staff on the project
• Other projects/assignments Team members are involved in that may conflict
• Calendars for materials and resources that will be needed
Float Time (additional time for an activity or path of activities that may be checked without affecting the duration of the project
Scheduling Checklist: Three points to remember?
Scheduling Checklist: What are some planning tool options?