What is project scheduling?
The process of defining project activities, determining
their sequence, and estimating their duration.
When is a project schedule typically created?
During the project initiation and planning phases.
What are the top challenges in project scope?
What is the ‘cone of uncertainty?’
A progressively more detailed and accurate projection of the project schedule and duration as the project manager or project team specifies project deliverables and activities in more detail.
What are the processes in the project schedule management process?
What are rough order of magnitude (ROM) estimates?
Important but inexact estimates occurring very early in a project’s life cycle—that may be used to justify a
project’s consideration.
What are Budgetary estimates?
Estimates that occur later as the various project components are specified in greater detail.
What are definitive estimates?
Estimates that are developed when the project’s resources and activities are highly detailed - and therefore only have a minor degree of potential error.
What is a work breakdown structure?
A WBS is a way to illustrate the project’s scope and as a launching point for describing the activities necessary for creating the various subcomponents of the project.
What is a work breakdown structure similar to?
A product breakdown structure.
What are the inputs a PM uses to create a WBS?
What is the primary process for creating a WBS?
Decomposition.
What is ‘rolling wave planning’?
A scheduling technique in which the team defers breaking down components until they are further clarified and the decomposition takes place as the project progresses.
What are different methods for working out the high level deliverables in the WBS
What is the ideal time for a work package within a work breakdown structure
No less than 8 hours, no longer than 80.
What is a Gantt Chart
Gantt charts help teams to plan work around deadlines and properly allocate resources. Projects planners also use Gantt charts to maintain a bird’s eye view of projects. They depict, among other things, the relationship between the start and end dates of tasks, milestones, and dependent tasks.
What is a scope baseline?
A document containing the WBS and the WBS Dictionary that specifies the deliverables and components of a project and serves to measure any deviations from that baseline during project execution..
What is a WBS dictionary?
A document that accompanies the WBS and provides additional information about the individual components of the WBS.
What does the defining activities stage involve?
In this stage, the different work packages of the WBS are broken down into discrete activities, and the attributes of these activities are defined, including a description, resource requirements, logical predecessor or successor activities, and the like.
What are the tools and techniques a PM can use to define activities in a WBS?
What is a work package?
A work package can be thought of as a sub-project, which, when combined with other work package units, form the completed project.
What are the typical features of an activity?
What is a network diagram?
A network diagram is a schematic display that illustrates the various activities (or tasks) in a project
as well as their sequential relationships
What is a dependency?
The process of determining relationships and logical sequence among activities.