TP 502 Flashcards

(5 cards)

1
Q

What are three sub processes within the planning process?

A

1) strategic planning. (10 years- 3 years out)
2) tactical planning. (2 years-1 year out)
3) operational planning. (1 year-30 days out)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is responsible for planning less than 30 days out?

A

OM and SSE via SVOP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of strategic planning? (10- 3 years out).

A
  • Determine work priorities.
  • Determine forecast spend and outage resource requirements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of tactical planning? (2- 1 year out).

A
  • Schedule maintenance, refurbs and new connections.
  • Handed over to ops once agreed by SO.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of operational planning? (1 year- 30 days out).

A
  • Allocates names to jobs.
  • PL to be given 90days notice via RPO?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly