The risk mitigation strategy, RISK CONTROL, involves which ONEof the following?
Taking action to reduce the likelihood, and/or occasionally the consequence of the risk to as low
as possible.
Which ONE of the following is NOT an activity program office personnel will perform during risk
analysis?
Determine if risk mitigation actions are effective.
Fill in the blank with the correct answer: “Risk identification deals with examining all elements
of the program to detect and document risks and their associated root causes. It basically answers the question:
What can go wrong?
A system can be defined as:
All elements (e.g.. hardware, software, logistical support, personnel) needed to assist the Department of Defense (DoD) to conduct its mission of deterring or winning war.
Which of the following institutions issues directives and regulations and formulates, directs, and executes national security policy?
The Executive Branch
Who provides an independent assessment of the effectiveness and suitability of new weapon
systems?
Director, Operational Test & Evaluation (D,OT&E)
If a Program Manager’s current estimate indicates a potential breach of the Acquisition Program
Baseline (APB) the Milestone Decision Authority (MDA) should be notified______________.
Immediately
Which of the following Acquisition Categories (ACATs) are established for services EXCEPT the Air Force and Space Force?
Acquisition Category (ACAT) IV
In order to be successful in acquisition management, which of the following SCHEDULE risk factors must be assessed.
Late deliveries
Select the Department of Defense’s (DoD’s) decision-support system described as: “DoD’s
primary resource allocation process that is calendar-driven.”
Planning, Programming, Budgeting and Execution (PPBE)
Which document is developed next if the Capabilities-Based Assessment (CBA) recommends a
materiel solution?
Initial Capabilities Document (ICD)
Which risk management option includes reassigning or delegating responsibility for tasks to
mitigate a risk to another entity?
-Risk Avoidance
Risk Transfer
Which opportunity management option includes intentionally ignoring an opportunity because of cost, technical readiness, resources, schedule burden, and/or low probability of successful
capture?
Reject
The Defense Security Cooperation Agency asks a Military Department to engage their acquisition
counterparts in allied and friendly nations regarding the potential benefits of acquiring an upgraded U.S. system that could provide additional coalition capability in the region in order to bolster the U.S. influence in the region. This initiative supports the achievement of which DoD Security Cooperation objective?
-Combine Exercises
Equipment Sales and Financing
What is the agreement between the Milestone Decision Authority (MDA) and Program Manager
(PM) that will be used for tracking and reporting for the life of a program?
Acquisition Program Baseline (APB)
Which of the following did the adoption of Joint Capabilities Integration and Development
System (JCIDS) allow DoD to do?
Shift from a threat-based approach to identifying warfighter requirements to a capabilities-based
approach
Select the document that establishes procedures and policies that assists the Chairman of the
Joint Chiefs (CJCS) in identifying, assessing and prioritizing joint military needs.
CJCSI 5123.01, Charter of the Joint Requirements Oversight Council and Implementation of the Joint Capabilities Integration and Development System (JCIDS)
This phase’s purpose is to mature the technology and reduce engineering, integration, and life
cycle sustainment cost risks to the point where a major development contract can be awarded with high confidence for the next phase.
Technology Maturation and Risk Reduction Phase (TMRR)
In which phase of the Major Capability Acquisition Pathway (MCA) is a program required to conduct an Operational Assessment (OA) and Logistics Demonstration?
Engineering and Manufacturing Development Phase (EMD)
Which of the following is NOT conducted during the Production and Deployment (P&D) Phase?
Development Request for Proposal Release Decision (DRFPRD)
The DoD Adaptive Acquisition Framework (AAF) supports the Defense Acquisition System (DAS)
with the objective of delivering __________ suitable, survivable, sustainable, and affordable solutions to the end user in a timely manner.
Effective
Who is responsible for the Planning and Programming phases of the Planning, Programming, Budgeting, and Execution (PPBE) System?
Director, Cost Assessment and Program Evaluation (D, CAPE)
Which DoD Security Cooperation objective is used to preserve peace through strength and
enhance U.S. coalition warfare capability through the establishment of international acquisition
partnerships with allied and friendly nations?
International Armaments Cooperation
_______ are events that may or may not occur that have the potential for improving the program in terms of cost, schedule, and performance.
Opportunities