Untitled Deck Flashcards

(100 cards)

1
Q

A project team only requires one more point for LEED platinum status and is investigating the IN credit category. Which action would NOT earn a project an Innovation credit for a LEED BD+C: New Construction project?

Development of a public education program
Achieving the pilot credit for ergonomics
Designing a net-zero building
Implementing a green cleaning policy and program
Using a new strategy to mitigate the heat island effect

A

Answer: Using a new strategy to mitigate the heat island effect

Explanation:
The HIE is already targeted in existing LEED credits within the scope of the system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The heat island effect for the most part occurs in downtown urban areas and the most effective strategy to mitigate it would be to:

Covering non-roof and roof surfaces with a three year aged solar reflectance value of at least 0.28
Put parking underground
Planting with native/adaptive species
Limiting the amount of hardscapes on the site and increasing the landscaping area

A

Answer: Limiting the amount of hardscapes on the site and increasing the landscaping area

Explanation:
N/A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A new development implemented an ESC (Erosion and Sedimentation Control) plan and LID (Low impact development) throughout its site which helps with 2 of the following: (CHOOSE 2)

Energy demand response program
The creation of buffers between development and water resources
On-site rainwater management
Walkability to diverse uses
Increase of the floor-area ratio
Reducing the heat island effect

A

Answer:
The creation of buffers between development and water resources
On-site rainwater management

Explanation:
You should break this down into 2 questions:
What does LID aid?
What does erosion and sedimentation control aid?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The MR Credit Building Disclosure and Optimization require that a product’s material ingredients be reported to at least 0.1% (1000 ppm) through which of the following documentation options? (CHOOSE 3)

Health product declarations (HPD)
Type II EPD
Type III EPD
Manufacturer inventory
Cradle-to-Cradle analysis

A

Answer:
Health product declarations (HPD)
Manufacturer inventory
Cradle-to-Cradle analysis

Explanation:
EPDs are not for material ingredient reporting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What must be submitted if a project team is able to achieve proper xeriscaping? (Select 2)

A description of the plants
A site plan showing the location of any temporary sprinkler heads
An indication of why average rainfall will be sufficient
A water budget
Type of irrigation system

A

Answer: A description of the plants
An indication of why average rainfall will be sufficient

Explanation:
A site plan would include the location and types of vegetation, not where sprinkler heads are installed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The following item must be included in the OPR but can be omitted from the commissioning prerequisite:

Building envelope
Process equipment
Renewable energy system
Monitoring systems
Domestic hot water boilers

A

Answer: Building envelope

Explanation:
Mechanical, electrical, plumbing, and renewable energy systems and assemblies must be commissioned for the prerequisite. The OPR must include the building envelope, it doesn’t have to be commissioned but can be done at request from the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A mechanical engineer and LEED consultant are unsure of how to define a sink in a retail-commercial-condo building and should:

Select a private sink
Select a public sink
Exclude the sink and assume EPAct 1992 compliance
Select the sink that has the greater flow rate

A

Answer: Select a public sink

Explanation:
Default to public use flow rates when performing the calculations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What section in LEED tries to streamline the requirements of different project types?

LEED Accreditation
LEED Market adaptations
LEED certification process
LEED Impact categories
LEED Addenda

A

Answer: LEED Market adaptations

Explanation:
The process of making adaptations to existing ratings systems and their credits provides an efficient and streamlined approach for responding to the particular needs, constraints, and opportunities of different project types

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If OPTION 3 – Daylight Measurement is pursued to show compliance with the EQ credit for daylight and the first lighting measurement is completed in January, what must occur to meet the credit?

The project will meet the credit as long as the January measurement showed compliance
A CIR is required to determine if another measurement must be taken
A second set of measurements must be taken in June
Documentation must be submitted for the January measurement to address non-compliant spaces

A

Answer: A second set of measurements must be taken in June

Explanation:
n/a

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

LeadingGreen is expanding and on a hiring binge because everyone loves sustainability. Luckily their current office was constructed with this in mind and the following item allows for flexibility in their growth:

Extra parking deck floors
Leasing systems furniture
Installing LEED approved projects
A vegetated roof
Demountable partitions

A

Answer: Demountable partitions

Explanation:
Demountable partitions are one strategy for designing for flexibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

At which stage in the project should all stakeholders be brought into the discussions to maximize effectiveness?

Discovery
Occupancy, operations, and performance feedback
Implementation
LEED Review

A

Answer: Discovery

Explanation:
The Discovery phase is when everyone needs to gather their ideas and consider synergies across LEED credits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What 3 items meet the requirements of an ESC plan?

Cover soils with products including mulch, tarps, filters, and fabrics so that soil won’t erode.
Install structural controls such as earth dikes, silt fences, sediment traps, and catch basins to divert water and to capture sediment from the storm water runoff.
Incorporate grade changes as necessary to allow construction vehicles access to the site.
Plant vegetation such as grass, ground covers, trees, and shrubs to stabilize soils.
Remove all hazardous trees and trees under a 40% condition rating.

A

Answer:
Cover soils with products including mulch, tarps, filters, and fabrics so that soil won’t erode.
Install structural controls such as earth dikes, silt fences, sediment traps, and catch basins to divert water and to capture sediment from the storm water runoff.
Plant vegetation such as grass, ground covers, trees, and shrubs to stabilize soils.

Explanation:
N/A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

LeadingGreen is trying to earn an additional point in the WE credit for cooling towers and is thinking about blending potable water and purple pipe water to feed the tower make-up water and meet the 20% of alternative water sources required. Which of the following is true in regards to this strategy?

Blending purple pipe water is not allowed in LEED
Both water types should be tested first
The commissioning agent would need to provide a training manual for this process
Blending is not allowed for this specific LEED credit only

A

Answer: Both water types should be tested first

Explanation:
The different water types should be tested to see what dissolved solids exist.
Potable water with high phosphates and a reclaimed water supply with high calcium may form calcium phosphate, which will lead to scaling in the
condenser.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Taking a look at the MR Prerequisite Storage and Collection of Recyclables which of the following stakeholders can provide the best suggested approaches for the best infrastructure required for collection?

A waste hauler or recycling provider
Building occupants
An owner or developer
The Civil Engineer

A

Answer: A waste hauler or recycling provider

Explanation:
E.g. If there will be dumpsters in the back of the building, can the trucks get to and load them? If a compactor will be on site, where is the best place to put it?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the scope of an Environmental Product Declarations (EPD)?

Gate-to-gate
Cradle-to-gate
Cradle-to-grave
Cradle-to-cradle v2
ISO 14044

A

Answer: Cradle-to-gate

Explanation:
N/A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Tridel Development is attempting to select a site that meets the requirements of the regional conservation authority while still satisfying the LEED credit for LT Credit Sensitive Land Protection. Which would meet the minimum distance requirements?

A site within 60 feet of a natural wetland
A site 50 feet from a river stream
Undeveloped land 40 feet from an artificial stream
A greenfield which is 40 feet from an artificial wetland

A

Answer: A site within 60 feet of a natural wetland

Explanation:
Sites should be at least 50 feet (15 meters) from wetlands, including previously developed and undeveloped land.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Parking garages are excluded from LEED certification and in turn actually have one of their own certification tools called Certified Green Garages – Green Parking Council. A certified green garage is constructed adjacent to our project and shares 50 of its spaces out of its 100. How should we account for them?

By including the 50 shared spaces minus disabled parking spaces
By including the 50 shared spaces
By including all 100 spaces
By including the 5% of total parking deck capacity

A

Answer: By including the 50 shared spaces

Explanation:
N/A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

If PCL Construction is able to obtain a construction general permit (CGP) then:

The civil engineer and landscape architect would need to stamp all drawings
A project hydrologist must conduct a site evaluation
An ESC plan is not needed
The project team must conduct a site assessment

A

Answer: An ESC plan is not needed

Explanation:
N/A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A project is located in Joshua Tree national park and is naturally pursuing LEED certification. It has all of the following features listed below and wants to know which are exempt for light trespass requirements?

National flag, the amphitheater, and the roadway
Roadway, national flag, and parking lot
Parking lot, roadway, and paths
Paths, landscape lighting, and parking lot

A

Answer: National flag, the amphitheater, and the roadway

Explanation:
List of Exempt lighting:
• specialized signal, directional, and marker lighting for transportation
• lighting that is used solely for façade and landscape lighting in MLO lighting zones 3 and 4, and is automatically turned off from midnight until 6 a.m.
• lighting for theatrical purposes (stage, film, and video performances)
• government-mandated roadway lighting
• hospital emergency departments, including associated helipads
• lighting for the national flag in MLO lighting zones 2, 3, or 4
• internally illuminated signage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A project is trying to maximize its points in the Energy + Atmosphere Credit Category and is focussing on achieving two points for EA Credit Green Power and Carbon Offsets by:

Purchase a combination of green power and carbon offsets equal to 50% of the project’s cost annually
Purchasing scope 1 and 2 RECs for electrical usage
Purchase a combination of green power and carbon offsets equal to 50% of the project’s energy (kWh)
Consuming zero net energy on an annual basis
Purchasing scope 1 and 2 RECs for electrical usage

A

Answer: Consuming zero net energy on an annual basis

Explanation: Net-zero buildings get the two points without purchasing any additional green power, RECs, or carbon offsets.
All other projects must have a 100% offset for two points.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

There is a piece of awkwardly shaped land that the project team excluded from the LEED project boundary which happened to help them earn an extra point. Which of the following is true?

This is not allowed in LEED
This is allowed if an investment in a land trust alliance equal to the land excluded
This is allowed if the land excluded is undeveloped
This is allowed in LEED if the piece of land has anything to do with regular business operations

A

Answer: This is not allowed in LEED

Explanation:
This is called gerrymandering and is not allowed. All the other options are incorrect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How long must the contract be if a project hopes to earn any points in the EA credit for Green Power and Carbon Offsets?

One (1) year with the intent to renew for multiple years
2 Years
5 months
As long as it takes to offset scope 1 emissions
5 years
1 year

A

Answer: 5 years

Explanation:
1 year with intent to renew is for demand response enrollment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Why should a project team submeter during the design phases of a new construction project? (CHOOSE 2)

The efficiency of the subsystems will increase depending on the submeter location
The meters can be located in places that can be read manually
It will be impossible to submeter some systems later on
A building automation system can be included to read the meters

A

Answer:
The meters can be located in places that can be read manually
A building automation system can be included to read the meters

Explanation:
The idea here is that submeter placement should be thought about during the design phase as early on as possible to make sure they are placed in the correct location and easily installed during construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

For the WE Credit for indoor water use a LEED consultant in assisting gathering all the correct information and has submitted each fixture type and its flush rate. What else is missing in the calculator? (Choose 2)

Gender ratio of the occupants using the toilet
The percent of alternative water (if any) used when flushing the toilet
Manufacturer and model
Percentage of occupants using the toilet

A

Answer:
Manufacturer and model
Percentage of occupants using the toilet

Explanation:
In the calculator teams will enter:
• Type of fixture
• Flush or flow rate
• Manufacturer and model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Data centers require slightly different items because of their unique usage over their life and many prerequisites/credits would benefit from having the two following members as principle participants on their project team: LEED AP BD+C and a budget oriented developer LEED AP BD+C and a qualified CxA Two LEED AP BD+C LEED AP BD+C and LEED AP O+M
Answer: LEED AP BD+C and a qualified CxA Explanation: In LEED v4, the LEED AP credit in the Innovation category can earn one point by having a LEED AP with the appropriate specialty on the project.
26
A new building in Manhattan is being constructed to the borders of its property line. It has a native/adaptive vegetated roof of 25 000 SF on a previously developed site. The building footprint is 50 000 SF and has a FAR of 1.55 as well as 12 DU/acre. What credit would this project not be eligible for? LT Credit High Priority Site SS Credit Open Space LT Credit Surrounding Density and Diverse Uses SS Credit Site Development – Protect or Restore Habitat
Answer: LT Credit High Priority Site Explanation: Because the FAR is greater than 1.5 the vegetated roof will count towards open space. The project could earn the protect/restore credit because more than 30% of the previously developed site was restored and the density is greater or equal to 12. There is not enough info for High priority site.
27
Installing occupancy sensors would not impact which credit in a brand new mixed-use office building? EQ Credit Enhanced IAQ Strategies EA Prerequisite Minimum Energy Performance EQ Credit Thermal Comfort EQ Prerequisite, Minimum IAQ Performance
Answer: EQ Credit Enhanced IAQ Strategies Explanation: Occupancy sensors are not part of monitoring outdoor air delivery. Occupancy sensors can be integrated in the design to turn down the thermostat automatically and reduce airflow when occupants are away, helping to reduce energy use. Occupancy sensors will decrease/increase the temperature in the building which can change the indoor air quality. EQ Credit Enhanced IAQ Strategies requires individual comfort controls. Occupancy sensors are not a type of individual comfort control. They are used for groups or areas rather than the individual.
28
In a brand new school how much refrigerant is permitted in the form of CFCs? None 2% if it will be phased out 20% if it is a non-impact CFC 5% if it has a low refrigerant charge
Answer: None Explanation: There is no reason why a new building should use CFCs. This is not a major renovation so phasing it out is nonsense and the other options are incorrect.
29
Which option would be the best location for MERV rated filters? On all return ducts At each local distribution point On each of the 2 outdoor air systems On the diffusers and exhausts
Answer: On each of the 2 outdoor air systems Explanation: Filters must also be replaced after completion of construction and before occupancy. The other options would not benefit from filtration especially on exhausts. Why filter what is leaving?
30
Which of the following items must be documented as part of the integrative process’ only credit? The ongoing commissioning plan The Owner’s project requirements (OPR) and basis of design (BOD) Current facility requirements (CFR) and Cx plan Construction documents and daylighting analysis
Answer: The Owner’s project requirements (OPR) and basis of design (BOD) Explanation: N/A
31
The EPA has a lot of standards that help with many aspects of the built-environment. Which of the following EPA tools assists with setting goals for energy efficiency? EPA Energy Star Portfolio Manager EPA Energy Star Target Finder EPA’s ASHRAE 90.1 Standard EPA Energysense label
Answer: EPA Energy Star Target Finder Explanation: The target is set in Energy Use Intensity through this tool.
32
LEED V4 condensed 5 low-emitting credits into one and streamlined its requirements. How can product compliance be demonstrated through documentation? (CHOOSE 3) Third-Party Certification Testing Reports Environmental Product Declaration Health Product Declaration MSDS sheets Manufacturing Engineer’s stamp
Answer: Third-Party Certification Testing Reports MSDS sheets Explanation: N/A
33
A LEED Project needs 3 more points to become LEED Certified after the preliminary review has been completed. What can be done? Install vertical bike racks to earn an EP point Reapply excluding 10% of the GFA to improve energy performance Exclude a portion of the land which restricts them from satisfying credit requirements Submit new documentation for credits that were denied or apply for other credits
Answer: Submit new documentation for credits that were denied or apply for other credits Explanation: This is allowed after a preliminary review
34
How can a project count a transit stop that has service in both directions and is within ½ mile from 1 of 5 functional entries in a building? This is not eligible for the credit as not all functional entries are within ½ mile Both directions can be counted as separate towards the credit Only trips from one of multiple stops in the vicinity and only trips in one direction are counted A site served by 2 diverse means of transit which neither provide 60% of the total trips would count for extra points
Answer: Only trips from one of multiple stops in the vicinity and only trips in one direction are counted Explanation: This is the only correct answer that we have enough information for. Not all functional entries must be within walking distance. Although a site served by 2 diverse means of transit which neither provide 60% of the total trips would count for extra points. There is not enough information to confirm that this site is one of those.
35
A blackberry (RIP) project which PEMI consulted on in Waterloo Ontario was using a historic building that could not meet the 10 foot long mat requirement. Who must address this item? LEED technical customer service The project administrator A member of the technical advisory group GBCI certification reviewer The city councillor
Answer: GBCI certification reviewer Explanation: If a project team needs guidance on an issue before submitting for certification review, the project CIR process is available to them. The project CIR will be determined by a GBCI Certification Reviewer familiar with the project’s specific circumstances.
36
A bank is located within walking distance of a grocery store and a restaurant would meet the LT Credit Surrounding Density and Diverse Uses if: The project could earn the credit if 1 more use in a different category is in the vicinity The project could not count itself as a service and thus would not earn the credit It already satisfies the requirements The project could earn the credit if 1 more use in a category is in the vicinity
Answer: The project could earn the credit if 1 more use in a different category is in the vicinity Explanation: • A minimum of 4 uses are needed • A use type only counts once • Uses must come from at least 3 of the 5 categories, exclusive of the building’s primary use • No more than two uses of each type (maximum of 2 restaurants for example) • Uses that are planned count if they are available within one year of LEED occupancy. • Food retail • Community-serving retail • Services • Civic and community facilities • Community anchor uses (BD+C and ID+C only)
37
Reducing light pollution has become a fairly complicated credit in LEED version 4 and does not account for which of the following? Exterior light outside the project boundary Backlight Internally illuminated exterior signage Light Trespass
Answer: Exterior light outside the project boundary Explanation: The credit requires: 1. Meet uplight requirements 2. Meet light trespass requirements 3. Meet internally illuminated exterior signage requirements
38
A new construction project will be used for 25 000 employees daily and includes rain water cisterns for toilets and only WaterSense fixtures. If the project is pursuing the WE Credit Indoor Water Use Reduction it would not need to include which of the following in the narrative for the non-potable reuse portion of the system? A maintenance schedule of the system A plan to deal with rain water contaminants Manufacturer cutsheets for the rainwater system The occupancy rates and numbers A plumbing system design drawing
Answer: A plumbing system design drawing Explanation: N/A
39
Exclusions are an important part in LEED and are also difficult to remember all the details. But, they also follow a pretty logical rhythm and as a result which water-using equipment can be excluded from the 20% reduction threshold of WE Prerequisite Indoor Water Use Reduction? (CHOOSE 3) Hotel lobby sink Eye-wash rinse in a laboratory Fixtures regulated by health codes coffee-making machines Public sink Residential dishwasher
Answer: Eye-wash rinse in a laboratory Fixtures regulated by health codes coffee-making machines Explanation: If it is water used for human consumption then it is not included.
40
Public transit is a large part of reducing the impact on global warming due to transportation. Which of the following items would not be included in the integrative process discovery phase for energy related research? Potential building features Local climate Site conditions Proximity to public transportation
Answer: Proximity to public transportation Explanation: Public transportation proximity does not have a significant (if any) impact on the building’s energy use.
41
The EA Credit Demand Response is new to LEED V4 and is quite forward thinking as it helps shift loads in attempt to minimize peaking. How can a DR event be initiated? An independent system operator sends a DR event over the Internet and the BAS initiates it automatically An independent system operator sends a DR event over the Internet and the facility manager initiates the event manually A text message is sent to an automated system which the facility manager must permit for a DR event initialization A utility company makes a phone call to a DR coordinator that initiates a control strategy programmed into a BAS.
Answer: An independent system operator sends a DR event over the Internet and the BAS initiates it automatically Explanation: Manual initiated events are not acceptable.
42
Utilizing the natural landscaping to incorporate shading will result in the following possible outcomes for a building owner: (CHOOSE 2) Increase energy load for electrical lighting Additional heating requirements in the summer months Reduce cooling load requirements High maintenance costs Higher cooling requirements
Answer: Increase energy load for electrical lighting Reduce cooling load requirements Explanation: Shading will help cool the building and also decrease the opportunities for daylighting, increasing the need for electric lighting.
43
How can the new prerequisites, which require building level energy/water metering, help with another credit? Educating occupants as to which end use consumes the most energy Supporting the commissioning authority Understanding the systems that are using the most energy Developing a strategy to respond to a DR event
Answer: Supporting the commissioning authority Explanation: Metering the energy/water will help with the analysis in supporting the commissioning authority during the ten-month review for Enhanced Commissioning.
44
Once the lighting zone of a site is established how would one go about creating the lighting boundary? It must follow the LEED project boundary It must follow the developed area of the site It must follow the property line It can differ from the project boundary if the change is justified
Answer: It can differ from the project boundary if the change is justified Explanation: N/A
45
When calculated a LWR landscape water requirement for a school what can be optionally excluded? Athletic field Mulched playground area Impervious parking lot Pervious walkways Hardscapes (pervious or impervious)
Answer: Athletic field Explanation: Hardscapes (pervious or impervious) MUST BE excluded while athletic fields can be included/excluded at the project teams’ discretion. Optionally included items: • Athletic field • Vegetated playground • Food garden • Urban agricultural area These areas must be excluded: • Hardscapes (pervious or impervious) • Unvegetated softscapes (mulched paths, playground areas)
46
How can the EA credit for demand response be pursued if the team does not meet the EA credit for optimizing energy performance and has to use the prescriptive compliance path for the minimum energy performance perquisite? A model is required for the demand response credit and thus it cannot be pursued The project team can use space peak-load calculations to calculate the minimum reduction in peak electricity demand The project can enrol in a permanent load shifting program to pursue the credit The project must generate 10% of its energy from on-site renewables to pursue the credit
Answer: The project team can use space peak-load calculations to calculate the minimum reduction in peak electricity demand Explanation: Models are not required nor is permanent load shifting available in BD+C as it is in O+M
47
A new shopping center is pursuing LEED BD+C Retail and plans to house 130 FTEs and 5000 peak visitors. There will also be 250 employee spaces and 500 visitor parking spaces. The credit wants to comply with LT credit for green vehicles which would be accomplished by: 38 preferred parking spaces and 8 alternative fueling stations 38 preferred parking spaces 15 of which have alternative fueling stations 38 preferred parking spaces and 15 alternative fueling stations 3 preferred parking spaces and 0 alternative fueling stations 75 preferred parking spaces and 8 alternative fueling stations
Answer: 38 preferred parking spaces and 15 alternative fueling stations Explanation: For LT Credit Green Vehicles, 5% of parking must be preferred, and 2% of parking must have a fueling station. The two cannot be combined. Remember to round up.
48
A project team needs one more point to reach LEED Platinum and is exploring creating a new Innovation in design program for placing an interactive dashboard with building information in the lobby. What is true about this proposed credit? This would not be eligible since there is a prerequisite addressing recycling these items If all the batteries are recycled and the owner signs off on the agreement then this would work IN Credit Innovation can only be earned if all occupants of the building are allowed to participate in the program A LEED AP would have to sign off of this credit for it to count
Answer: IN Credit Innovation can only be earned if all occupants of the building are allowed to participate in the program Explanation: The three basic criteria for achieving an IN credit for a category not found in the LEED rating system are as follows: • Quantitative – this means the concept must have measurable/quantifiable environmental benefits. Establish a baseline and compare it with the final outcome to determine the improvement. How much environmental benefit did the strategy achieve? • Comprehensive – the process or specification must be comprehensive. For example, if a new material could be used in every floor of a building, the project team can’t use it in just one floor. A process that only addresses a part of the project isn’t considered comprehensive and does not meet the credit requirements. • Transferrable – the concept must be able to be used on other projects by other project teams. It can’t be a concept that only applies to a unique aspect of one project.
49
A development team is trying to find a site that is located near a bike network but wants your help to properly explain what it is? Streets with a maximum speed limit of 30 mph without dedicated bicycle stripes A continuous network of bike trails A separated bike lane on a graded road A bike path through a park
Answer: A continuous network of bike trails Explanation: This is the best description. Bicycle Network – a continuous network consisting of any combination of the following: • off-street bicycle paths or trails at least 8 feet (2.5 meters) wide for a two-way path and at least 5 feet (1.5 meters) wide for a one-way path • physically designated on-street bicycle lanes at least 5 feet (1.5 meters) wide • designed for a target speed of 25 mph (40 km/h) or less
50
For the WE Prerequisite Indoor Water Use Reduction, how would using an evaporative condenser that uses 100% potable water affect it? The team would need to blend the water with non-potable sources The team would need to add a meter for makeup water The team would need to increase the number of cycles of concentration The team would need to hire a water treatment professional to conduct a one-time potable water analysis
Answer: The team would need to add a meter for makeup water Explanation: The prerequisite requirements for cooling towers and evaporative condensers are to make sure the equipment has: • makeup water meters • conductivity controllers and overflow alarms • efficient drift eliminators
51
A building has a large surface level parking lot and they calculated the amount of runoff needed for the 95 percentile storm. In the credit for storm water runoff, how much of that 95 percentile must be managed? Only the runoff from the impervious areas of the site Only the runoff from the previously developed area 95% of the total site runoff 100% of total site runoff 25% of all impervious surfaces
Answer: 100% of total site runoff Explanation: The strategies used must manage 100% of the runoff volume for the entire developed site. 25% of all impervious surfaces is for an existing building.
52
Conservation is an important strategy for reducing the overall demand of water and energy consumed in a building. As source reduction is a tool used to help another area of the building, which of the following is not an example of source reduction? Purchasing salvaged wood Cutting wood to exact lengths at the supplier level Reduced packaging Modular building elements
Answer: Purchasing salvaged wood Explanation: Salvaged wood helps with other credits but it is not ensuring there is no waste from the source/manufacturer/supplier.
53
Which of the following is a benefit of a site analysis? To meet the SS credit for open space Streamline the LT and EQ prerequisites To identify synergies between the assessment and other LEED credits To protect and or restore habitat while achieving the IP Credit
Answer: To identify synergies between the assessment and other LEED credits Explanation: N/A
54
Looking at the IP Credit which of the following must be completed in the simple box energy modeling before completion of schematic design? At least two synergies between water and energy At least one load reduction strategy and one energy efficiency strategy At least one on-site renewable source At least two potential load reduction strategies At least one way to increase efficiency
Answer: At least two potential load reduction strategies Explanation: N/A
55
Which of the following strategies would not help a project earn the first Materials and Resources Prerequisite? Conveniently placing recycling bins in a high traffic area Placing recycling bins beside the trash and organic bins Centrally locating the bins Placing bins in the parking garage
Answer: Placing bins in the parking garage Explanation: Recycling needs to be convenient and easy for both occupants and operations staff to get higher recovery rates
56
LeadingGreen wants to reduce energy consumption due to lighting as it is a major consumer and as a result only installs light in each work station. How can the architect increase lighting without specifying additional fixtures? Increase the window to floor ration Increase the window to wall ratio Design narrow floor plates to optimize daylighting Install exterior shading Install interior light shelves
Answer: Design narrow floor plates to optimize daylighting Explanation: Daylight can compensate for the reduced illumination levels due to task lighting.
57
A project in Houston is negatively affected by the heat island effect and thus consumes a lot of energy to meet cooling demands. How can this flat roofed zero-lot line project meet the credit’s exemplary performance threshold for reducing the heat island effect? Cover the entire roof with a material that has a 3 year aged SRI > 39 Construct a huge Solar thermal collector which encompasses the entire roof Construct a vegetated roof and build 100% underground parking Construct 100% of the parking underground
Answer: Construct a vegetated roof and build 100% underground parking Explanation: For exemplary performance, a project must achieve both Option 1 and Option 2 of the credit, and for Option 2, 100% of the parking must be under cover.
58
A LEED Charrette or goal setting workshop is crucial in the LEED process and should include the following actions: Creating a map outlining walking paths to diverse uses, selecting a vendor to purchase RECs from, reviewing power requirements of different energy consuming systems Collection of information about local climates, reviewing EPDs of materials, life cycle analysis of the building design Hearing from all community representatives, clarifying functional and programmatic goals, building operations training Engagement of the owner and primary project team, setting a target certification level, picking LEED credits and assigning responsibilities
Answer: Engagement of the owner and primary project team, setting a target certification level, picking LEED credits and assigning responsibilities Explanation: N/A
59
A waste management company is trying its best to divert 100% of the construction waste to meet the MR Credit Construction and Demolition Waste Management Option 1 Diversion and must include which of the following diversion calculations? Excavated soil Asbestos ceiling tiles Alternative daily cover (ADC) Carpet that is not Green Label Plus certified Land-clearing debris from cutting down trees and shrubs
Answer: Carpet that is not Green Label Plus certified Explanation: The carpet would need to be included in the calculations for the total of all construction waste management and the rest of the items are excluded
60
How can a concept pre-pre-design model help achieve the Integrative Process credit? It can be used to verify the prescriptive requirements are met for EA Prerequisite Minimum Energy Performance It can earn an exemplary performance point It can be used as the baseline model for a proposed design It can be used for healthcare projects It can form the basis of the preliminary energy model for a whole-building energy simulation
Answer: It can form the basis of the preliminary energy model for a whole-building energy simulation Explanation: When doing a whole-building energy simulation for EA Prerequisite Option 1, teams must engage a qualified energy modeller to create a preliminary model to aid in design decisions. This model will help as long as there is time to alter the design. The concept model prepared the project team to create the simple box energy analysis that is part of the Integrative Credit and that can be used as the basis of the preliminary model. The preliminary model analyzes building design configurations and heating and cooling load reduction strategies and is used for Option 1.
61
The EQ credit for Enhanced IAQ requires interior cross-contamination prevention. What is an example of achieving this in our imaginary office tower’s photocopy/printing room? Ventilate with 100% Outdoor air Weather strip all doors and windows Self-closing doors and deck-to-deck partitions Create a pressure differential across the spaces around it only
Answer: Self-closing doors and deck-to-deck partitions Explanation: Interior cross-contamination prevention requires: • exhaust each space (e.g., garages, housekeeping and laundry areas, copying and printing rooms) • using the exhaust rates as per EQp1 or a minimum of 0.50 cfm per square foot • Install self-closing doors and deck-to-deck partitions or a hard-lid ceiling
62
A retirement home is located near absolutely nothing and thus cannot meet the MR Credit Construction and Demolition Waste Management Option 1 Diversion but should consider what strategy as a way to meet it? Store the waste in a secure area on site Use any untreated wood waste as biofuel Submit a CIR Documenting that the infrastructure is not compatible and as a result meet the credit
Answer: Use any untreated wood waste as biofuel Explanation: Waste-to-energy is a viable option if reuse and recycling is not available.
63
One of the requirements to provide quality interior lighting is meeting a CRI of 80+. What would specifying levels of illuminance below 2,500 cd/m2 assist with? Increasing daylight to save energy Approximating natural light Increasing maintenance costs by replacing lights more frequently Reducing glare
Answer: Reducing glare Explanation: The other options would help with the other choices. See the 8 items in the reference guide.
64
A whole building energy model cannot be conducted due to a number of extraneous variables and as a result a school decides to pursue ASHRAE 50% Advanced Energy Design Guide for K-12 School Building prescriptive path. The MEP has verified that the Ducts and dampers as well as the equipment’s efficiency meets the requirement, and must also verify which of the following? Interior lighting including daylighting and interior finishes Plug loads, including equipment and controls Lighting loads inside and outside Economizers and ventilation requirements Building envelope, glazing: vertical fenestration
Answer: Economizers and ventilation requirements Explanation: Prerequisite requirements: • Equipment efficiency • Economizers • Ventilation • Ducts and dampers Credit requires: • Building envelope, opaque: roofs, walls, floors, slabs, doors, continuous air barriers • Building envelope, glazing: vertical fenestration • Interior lighting (including daylighting and interior finishes) • Exterior lighting • Plug loads, including equipment and controls
65
A previously developed site in Rural Vaughn has the following characteristics: Total Site area = 500 000 SF Existing building footprint = 200 000 SF Hardscapes and impervious pavement = 10 000 SF How much must be restored for SS Credit Site Development-Protect or Restore Habitat? 240 000 210 000 150 000 90 000
Answer: 150 000 Explanation: 30% must be restored including building footprint 30% x 500 000 SF = 150 000
66
How are suggested approaches dealt with in the LEED review process when an issue in the LEED reference guide is not addressed? If the approach is accepted it can be precedent-setting and can be used in future project reviews A project CIR will need to be submitted immediately They will receive a determination in the review comments at the discretion of the reviewer assigned to the project The approach will be rejected immediately upon submission
Answer: They will receive a determination in the review comments at the discretion of the reviewer assigned to the project Explanation: When dealing with an issue not addressed in available LEED guidance material, project teams have the option of submitting a suggested approach duringthe standard LEED certification process.
67
Daylight has 3 options for compliance, 2 of which are met with simulation strategies and a project in Toronto requires a Spatial Daylight Autonomy of: Surface reflectance levels 80% for ceilings, 20% for floors, and 50% for walls Measurement using a handheld device to demonstrate Illuminance levels between 300 lux and 3,000 lux 9 AM on the first equinox (March 21 or September 21) and 3 PM on the second equinox 300 lux for 50% of the hours between 8 AM and 6 PM EST
Answer: 300 lux for 50% of the hours between 8 AM and 6 PM EST Explanation: The other options are all true for other options within the credit.
68
The USGBC Calculator splits genders and assumes half the FTEs are women and half are men except when the project is a: In a communal bathroom residence In an office with more than 70% male employees School exclusively for girls In a boys’ locker room of a public high school In an office with more than 70% male employees
Answer: School exclusively for girls Explanation: N/A
69
Which of the following items would help meet the 20-product minimum for the Building Product Disclosure and Optimization credits by counting as 2 separate products? Light gray acoustic ceiling tiles for a classroom and beige acoustic ceiling tiles for an auditorium from the same product line and manufacturer 2 different coloured paints from the same manufacturer A conference room elongated table and an identical miniature version – individual work station, each from the same product line and manufacturer Carpet tile for a lobby with low pile and carpet tile for an office with a higher pile, each from the same manufacturer
Answer: Carpet tile for a lobby with low pile and carpet tile for an office with a higher pile, each from the same manufacturer Explanation: The tiles serve different functions and would count as different products even though they are from the same manufacturer.
70
A project is short a few thousand dollars to meet the MR credit BPD+O material ingredient optimization. Which of the following product standards would contribute the most of the 25% requirement? (Choose 2) GreenScreen Assessment Cradle-to-Cradle v3 Gold certified GreenScreen List Translator LEED Approved USGBC approved
Answer: GreenScreen Assessment Cradle-to-Cradle v3 Gold certified Explanation: These 2 items are worth 150% of their cost when making this calculation.
71
Some of these questions are harder than others. Which is the most suitable site for a project to earn maximum points in the LT credit category? A previously developed site near similar projects Land that is the habitat for endangered species Previously undeveloped land with a 1% chance of flooding in any given year A previously developed piece of land near nothing at all A previously developed site near different projects
Answer: A previously developed site near different projects Explanation: This choice would meet LT Credit Sensitive Land Protection and potentially more credits
72
A project wants to eliminate all energy required for treating outdoor air through natural ventilation. The building would require an HVAC system if which of the following is true? The natural ventilation openings are operable during occupied hours The openings remain permanently open The naturally ventilated zone is not served by heating or cooling equipment. The system is not an engineered natural ventilation system approved by the authority having jurisdiction
Answer: The natural ventilation openings are operable during occupied hours Explanation: ASHRAE Standard 62.1–2010, Section 6.4, requires naturally ventilated spaces to include a mechanical ventilation system unless one of the following exceptions applies: • Ventilation openings comply with Section 6.4 and are permanently open. • Ventilation openings comply with Section 6.4 and have controls that prevent them from being closed during times of expected occupancy. • The naturally ventilated zone is not served by heating or cooling equipment. • The system is an engineered natural ventilation system approved by the authority having jurisdiction
73
Energy modeling is a growing field as municipalities adopt codes which mandate energy models for new construction projects. What is true in regards to a project which hires a modeler during the end of the design phase of the project? The influence and value of this model will be very small as design decisions have been made and it would be costly to improve The cost of the building would be reduced initially and over time The model cannot be used to measure the energy demand for EA Credit optimize Energy Performance The model cannot be used to measure the energy demand for EA Prerequisite Minimum Energy Performance. Energy modeling is integral to the integrative process credit
Answer: The influence and value of this model will be very small as design decisions have been made and it would be costly to improve Explanation: The model would still apply for the prerequisite and to earn points in the credit, but the model’s usefulness in influencing decisions would have passed by this point. In this scenario, the design is almost done. The project team can’t go back and earn the Integrative Process credit. But teams should conduct a simple box energy model during the IP.
74
A project has installed a creative energy saving building management device that saves non-regulated energy loads and the energy model should address this by: The savings would be cancelled out in both the baseline and design case model The exceptional calculation method would be used Manually figuring out the savings using an excel file Leaving it out of the calculation in total The non-regulated load is subtracted from both the baseline and design case model
Answer: The exceptional calculation method would be used Explanation: A non-regulated load is defined as any building load, end-use or control which does not have an ASHRAE 90.1-2010 baseline modeling requirement that allows the load and use or control to be modeled differently in the proposed and baseline buildings.
75
Metering is emphasized in the new version of LEED which is a great improvement as it’s a mandatory prerequisite. Which of the following items must be completely metered to achieve the WE Credit Water Metering? (Choose 2) Reclaimed water Domestic hot water Boilers Indoor plumbing fixtures and fittings Process Water
Answer: Reclaimed water Boilers Explanation: The other items can be measured to 80%+
76
Using hydro fluorocarbons (HFC) results in what kind of trade-offs? It has a higher GWP than HCFC It has a lower refrigerant charge May require more energy to achieve the same level of cooling as HCFC It has a high flammability
Answer: May require more energy to achieve the same level of cooling as HCFC Explanation: It has a lower GWP but requires more energy to achieve the same level of cooling.
77
On July 1 the USGBC published addenda for LEED BD+C. LeadingGreen’s project was registered in March and so was their reference guide. What do they need to do? (CHOOSE 2) The project team can choose to follow any addenda published after July 1 Follow all addenda published after July 1 Follow all addenda published before February Follow the relevant addenda only published before February
Answer: The project team can choose to follow any addenda published after July 1 Follow all addenda published before February Explanation: Project teams must follow Addenda published prior to their project’s registration date. It’s strongly recommended that project teams also follow Addenda published after their registration date.
78
Which of the following initial documents includes installation verification checklists, functional performance tests, issues log that details open and closed issues? A simple box energy model Owners project requirements Operations and Maintenance plan Commissioning Report Basis of Design
Answer: A simple box energy model Explanation: The point I was trying to drive home here was that the simple box energy model is the first thing done before the other 4 items and is the broadest to include the basis for the other 4 options. More for simple box – https://www.loraxllc.com/simple-box-model-its-as-simple-as-it-sounds/ Understand what the following documents entail: OPR | BOD | Cx Plan | Cx Report | CFR and Operations and Maintenance plan | Systems Manual (Enhanced Cx) | Ongoing Cx Plan (Enhanced Cx)
79
What would a vegetative roof help with? SS Credit Rainwater Management and SS Credit Heat Island Reduction SS Credit Rainwater Management and WE Indoor water use reduction SS Credit Heat Island Reduction and SS Credit Open Space SS Credit Rainwater Management and SS Credit ESC plan
Answer: SS Credit Rainwater Management and SS Credit Heat Island Reduction Explanation: We do not know if the FAR is 1.5+ and thus are not sure about the open space compliance
80
Alternative water sources are a great way to reduce potable water use in a cooling tower and to do this the following should be used: Graywater and steam system condensate Stormwater runoff from the property grounds and graywater Rainwater from building roofs and stormwater runoff from the property grounds Air conditioning condensate and rainwater from building roofs
Answer: Air conditioning condensate and rainwater from building roofs Explanation: Different sources of condensates – air conditioning, steam systems, ice machines – and runoff from a building’s roof require the least treatment. They havelow mineral content.
81
A new project is being built in an area with a high Dwelling Units per Acre and as a result is within walkable proximity to a number of diverse uses which mitigates environmental impacts from: (CHOOSE 2) Groundwater pollution due to construction Water pollution and sedimentation of nearby streams Bicycle pollution Greenhouse gas Air Pollution
Answer: Greenhouse gas Air Pollution Explanation: Locating a project near diverse uses helps promote walkability, transportation efficiency and reduce vehicle distance traveled while improving publichealth.
82
The city of Montreal is very bike friendly. What are the requirements for short term bike parking? A 100-feet walking distance of the main entrance A 100-feet walking distance of any functional entry A 100-feet bicycling distance to the bicycle network A 100-feet walking distance to a bank A 100-feet walking distance to the bicycle network
Answer: A 100-feet walking distance of the main entrance Explanation: • For short-term storage, the distance is to the main entrance, not every functional entry or the network. • For long-term storage, the distance is 100 feet of the functional entries. • The storage must be on site.
83
About less than half the credits have an exemplary performance option. Which of the following strategies would earn an EP? Doubling the highest transit service point threshold for alternative transportation Achieve 20% improvement in energy efficiency over the baseline ASHRAE 90.1 standard Creating a Green cleaning program as described in another LEED Rating system Achieve SS Credit Heat Island Reduction Option 1 Nonroof and Roof and SS Credit Heat Island Reduction Option 2 Parking Under Cover and place 75% of parking under cover, use 100% non-potable water for all flushing fixtures
Answer: Doubling the highest transit service point threshold for alternative transportation Explanation: LT Credit Access to Quality Transit can earn exemplary performance for this
84
If a material is salvaged from off-site, which of the following options are true when trying to calculate points based on the value ($) of materials versus a material’s surface area? - Surface area can be applied to MR Credit Building Life-Cycle Impact Reduction, Option 3 Building and Material Reuse and the cost can be applied to MR Credit Building Product Disclosure or Optimization – Sourcing of Raw Materials, Option 2 Leadership Extraction Practices. - The cost can be applied only to MR Credit Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2 Leadership Extraction Practices. - Surface area cannot be applied to MR Credit Building Life-Cycle Impact Reduction, Option 3 Building and Material Reuse and the cost cannot be applied to MR Credit Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2 Leadership Extraction Practices. - Its cost can be applied to MR Credit Building Life-Cycle Impact Reduction, Option 3 Building and Material Reuse and its surface area can be applied to MR Credit Building Product Disclosure and Optimization – Sourcing of Raw Materials, Option 2 Leadership Extraction Practices.
Answer: Surface area can be applied to MR Credit Building Life-Cycle Impact Reduction, Option 3 Building and Material Reuse and the cost can be applied to MR Credit Building Product Disclosure or Optimization – Sourcing of Raw Materials, Option 2 Leadership Extraction Practices. Explanation: • The reuse of off-site materials can be applied to only one credit. • Building reuse uses surface area. • The optimization credit option uses cost or replacement value.
85
A new office tower has a FAR of 2.5, a building footprint of 50 000 SF and a site area without a building footprint of 150 000 SF. Thus to achieve the SS credit for open space it would need to contain _____ SF of open space? 60 000 30 000 7 500 15 000
Answer: 60 000 Explanation: The total site area (including the building footprint) = 50 000 SF + 150 000 SF = 200 000 SF 200 000 x 30 % = 60 000 SF must be open 60 000 x 25% = 15 000 SF must be vegetated
86
In regards to the SS Prerequisite Construction Activity Pollution Prevention what is true? A compliant ESC plan can be initiated and designed at any time A CGP plan trumps the ESC plan If local zoning is less stringent it should be followed A compliant ESC plan must have been in place prior to construction to earn the prerequisite
Answer: A compliant ESC plan must have been in place prior to construction to earn the prerequisite Explanation: N/A
87
A new school’s project-team decides to use a waste-to-energy facility in order to meet the MR credit for Construction and Demolition Waste Management. What must be submitted for proper LEED documentation in this case? Waste tracking totals and diverted waste amounts only Justification for the use of waste-to-energy Methodology and results of the waste stream study Total waste per area
Answer: Justification for the use of waste-to-energy Explanation: Waste-to-energy needs to be justified. Additional documentation includes the facility adhering to relevant EN standards.
88
How can a project maximize its day light while minimizing solar heat gain due to daylighting strategies? Use a model to increase the window to wall ratio Exterior shading Only provide glazing from 30”-90”off the ground Increase the window to floor ratio
Answer: Exterior shading Explanation: The other options are not beneficial for minimizing SHGC and maximizing day light
89
LEED Does not certify or approve any products but it does accredit individuals and certify overall building sustainability as well as piggy back off of existing standards such as Watersense which could label which of the following? Private lavatory faucet Public lavatory faucet Waterless urinal Tankless toilet Composting toilet
Answer: Private lavatory faucet Explanation: The following can have a WaterSense label: • Tank-type toilets (water closet) • Water-using urinals • Private lavatory faucets • Showerheads The following are NOT eligible for WaterSense labels: • Tankless toilet • Composting toilet • Waterless toilet • Waterless urinal • Public lavatory faucet
90
Whole building energy and water modeling is a new prerequisite for LEED v4 and it discourages criticism from the public for lack of follow-up procedures. Which of the following would require submetering for the Advanced Energy Metering credit? (CHOOSE 2) Three air conditioning units that use 4% of total annual consumption of the building each A ventilation system which serves 10% of the regularly occupied space Direct overhead lighting which uses 15% of the total annual consumption of the building Five openings which provide 15% of the cooling from natural ventilation A vegetative roof with solar PV on top to cool it down
Answer: Three air conditioning units that use 4% of total annual consumption of the building each A ventilation system which serves 10% of the regularly occupied space Direct overhead lighting which uses 15% of the total annual consumption of the building Explanation: N/A
91
What is a differentiating factor between the three options available in the SS Credit Rainwater Management? The calculator used to determine rainfall The volume of runoff to manage The source of the rainfall data The type of LID strategies to follow
Answer: The volume of runoff to manage Explanation: The three options have different volume runoff requirements.
92
In a mixed use commercial-residential and retail neighbourhood a project wants to implement transportation demand reduction strategies which include: (CHOOSE 3) Transit Subsidy Scheduled work week Discourage telecommuting Shared Parking Residential Units sold separately from Parking Preferred parking for employees
Answer: Transit Subsidy Shared Parking Residential Units sold separately from Parking Explanation: Transportation demand management strategies include the following: • Telecommuting • Shuttles • Shared parking between uses • Residential units rented/sold separately from parking • Transit subsidies • Compressed workweek schedules
93
Leadinggreen is consulting on a project team and is listening to no/low cost strategies such as using high SR 40% unbound pavement for sidewalks which would not effect: SS Credit Open Space SS Credit Heat Island Reduction EA Credit Optimize Energy Performance SS Credit Rainwater Management
Answer: SS Credit Open Space Explanation: The pervious pavement choice will help with runoff and the other credits not selected.
94
When must a project team conduct an air-quality test for EQ Credit IAQ Assessment? (CHOOSE 2) During normal occupied hours and while operating at a minimum outdoor airflow rate When the ventilation system is providing 30% less outdoor air than required by ASHRAE 62.1 When the ventilation system is off Prior to building occupancy
Answer: During normal occupied hours and while operating at a minimum outdoor airflow rate Prior to building occupancy Explanation: Worst-case normal scenarios are to be tested by IAQ
95
Where would a Gaussian dispersal air intake model be used to demonstrate compliance? Carbon dioxide monitoring for densely occupied spaces Natural Ventilation minimum requirements Increased ventilation Additional source control and monitoring Exterior contamination prevention
Answer: Exterior contamination prevention Explanation: Exterior contamination prevention requires teams to design the project to minimize and control the entry of pollutants into the building. Teams demonstrate this through computational fluid dynamics modeling.
96
For the option of Building and Material Reuse in the MR Credit Building Life-Cycle Impact Reduction, which of the following items may not be reused as counted by surface area? (CHOOSE 2) Reused foundation Hazardous materials Interior Structural Walls Exterior Walls Window assemblies
Answer: Hazardous materials Window assemblies Explanation: N/A
97
The LEED BD+C: Core and Shell rating system is the appropriate rating system to use if more than 40% of the gross floor area is incomplete at the time of certification. What is not included in this rating system? (CHOOSE 2) Furniture, furnishings, and equipment (FF&E) Heating Ventilation and Air Conditioning Tenant fit-out The Structure Building Envelope
Answer: Furniture, furnishings, and equipment (FF&E) Tenant fit-out Explanation: FF&E are in LEED BD+C and ID+C while tenant fit outs are in ID+C.
98
Rain water can result in strain on municipal systems as well as pollution of adjacent streams. Which of the following items is required to determine the amount of rain water needed to manage in LEED under natural land-cover conditions? The natural land-cover volume and the post-development volume The total runoff volume of just the developed areas on the site The 85th percentile of rainfall events The evapotranspiration rates of all vegetation on the site
Answer: The natural land-cover volume and the post-development volume Explanation: 85th percentile is only used for zero-lot-line projects.
99
Where should fresh air intakes be located on a building to ensure maximum control of pollutants? One-third of the way up the side of the building Above the main entrance doors On the roof In the parking garage In the courtyard of the building beside Air handling units
Answer: One-third of the way up the side of the building Explanation: Air is best taken in at this location
100
In a brand new condo, looking at the MR Prerequisite Construction and Demolition Waste Management Planning, which stakeholder should be implemented into the team early on in the project to make it easier later on? Contractor Commissioning Authority Facility Manager All occupants on the condo board
Answer: Contractor Explanation: The contractor will be responsible for properly managing this credit.