Materials Price=
Actual Kg x budgeted price p/u-actual costs
Materials Usage
(Actual Units x KG p/u-Actual Material used) x Standard Material Price
Labour Rate
Labour hours worked x Standard Rate- Actual Cost of Labour
Labour Efficiency
(Units x Hour p/u-hours worked)xStandard Rate
Variable Overhead Rate
Variable Overhead P/U x Units-actual variable overhead
Variable Overhead Efficiency
(Hours p/u x actual units- actual hours worked) x Standard Variable Overhead
Fixed Overhead Expenditure Variance
Fixed Overhead p/u x unit-actual fixed overhead
Sales Price
Actual Sales units x standard price-actual revenue
Sales Volume
(Budgeted Sales units-actual sales units) x standard price