What is the period for a contractor to respond to a schedule 2 quotation?
21 days
What are disadvantages of a schedule 2 quotation
need to pay for the cost of putting it together even if the change isn’t instructed
Can an instruction go ahead without an agreed price?
Yes unless under a SBC a schedule 2 quotation has been requested