What are the 3 methods of Measurements?
Cross-Section Method
• Used almost exclusively for calculating volumes on linear construction projects. eg: Highways, Railways, Canals
• There are several typical cross sections encountered when calculating manually (from survey)
1) Level section (flat conditions)
2) Three-level section
3) Five-level section (rough topography)
4) Irregular section (rough topography)
5) Transition section (cut and fill)
6) Side-hill section (cut and fill)
• The areas of these sections are called “end areas”
Unit-Area Method
Contour Area Method
What are some considerations when taking volume?
What are the different types of Volume
• Bank volume
undisturbed volume
Volume in-place, in-situ
• Loose volume
Volume of excavated material (post excavation)
• Compacted volume
Volume of material after compaction