2. The work breakdown structure can BEST be thought of as an effective aid for communications. A. Team B. Project manager C. Customer D. Stakeholder
4. During project executing, a team member comes to the project manager because he is not sure what work he needs to accomplish on the project. Which of the following documents contains detailed descriptions of work packages? A. WBS dictionary B. Activity list C. Project scope statement D. Scope management plan
5. During which part of the project management process is the project scope statement created? A. Initiating B. Planning C. Executing D. Monitoring and controlling
Explanation The project scope statement is an output of the Define Scope process, which occurs during project planning.
6. The program was planned years ago, before there was a massive introduction of new technology. While planning the next project in this program, the project manager has expanded the scope management plan because, as a project becomes more complex, the level of uncertainty in the scope: A. Remains the same. B. Decreases. C. Decreases then increases. D. Increases.
9. During a project team meeting, a team member suggests an enhancement to the scope that is beyond the scope of the project charter. The project manager points out that the team needs to concentrate on completing all the work and only the work required. This is an example of: A. Change management process. B. Scope management. C. Quality analysis. D. Scope decomposition.
13. A new project manager has asked you for advice on creating a work breakdown structure. After you explain the process to her, she asks you what software she should use to create the WBS and what she should do with it when it is completed. You might respond that it is not the picture that is the most valuable result of creating a WBS. The most valuable result of a WBS is: A. A bar chart. B. Team buy-in. C. Activities. D. A list of risks.
15. A project manager may use to make sure the team members clearly know what work is included in each of their work packages. A. The project scope statement B. The product scope C. The WBS dictionary D. The schedule
17. The construction phase of a new software product is near completion. The next phases are testing and implementation. The project is two weeks ahead of schedule. Which of the following processes should the project manager be MOST concerned with before moving into the final phase? A. Validate Scope B. Control Quality C. Manage Communications D. Control Costs
18. You are managing a six-month project and have held bi-weekly meetings with your project stakeholders. After five-and-a-half months of work, the project is on schedule and budget, but the stakeholders are not satisfied with the deliverables. This situation will delay the project completion by one month. The MOST important process that could have prevented this situation is: A. Monitor and Control Risks. B. Control Schedule. C. Define Scope. D. Control Scope.
19. All of the following are parts of the scope baseline EXCEPT the: A. Scope management plan. B. Project scope statement. C. Work breakdown structure. D. WBS dictionary.
22. The development of the scope baseline can BEST be described as involving: A. The functional managers. B. The project team. C. All the stakeholders. D. The project expediter.
23. Which of the following is an output of the Collect Requirements process? A. Requirements traceability matrix B. Project scope statement C. Work breakdown structure D. Change requests