1. To control the schedule, a project manager is reanalyzing the project to predict project duration. She does this by analysing the sequence of activities with the least amount of scheduling flexibility. What technique is she using? A. Critical path method B. Flowchart C. Precedence diagramming D. Work breakdown structure
2. A dependency requiring that design be completed before manufacturing can start is an example of a(n): A. Discretionary dependency. B. External dependency. C. Mandatory dependency. D. Scope dependency.
3. Which of the following are GENERALLY illustrated BETTER by bar charts than network diagrams? A. Logical relationships B. Critical paths C. Resource trade-offs D. Progress or status
4. If the optimistic estimate for an activity is 12 days, and the pessimistic estimate is 18 days, what is the standard deviation of this activity? A. 1 B. 1.3 C. 6 D. 3
5. A heuristic is BEST described as A. Control tool. B. Scheduling method. C. Planning tool. D. Generally accepted rule.
7. Which of the following is the BEST project management tool to use to determine the longest time the project will take? A. Work breakdown structure B. Network diagram C. Bar chart D. Project charter
12. A project has three critical paths. Which of the following BEST describes how this affects the project? A. It makes it easier to manage. B. It increases the project risk. C. It requires more people. D. It makes it more expensive.
13. If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do? A. Perform a Monte Carlo analysis. B. Fast track the project. C. Perform resource optimization. D. Analyze the life cycle costs.
14. When is a milestone chart used instead of a bar chart? A. Project planning B. Reporting to team members C. Reporting to management D. Risk analysis
15. Your project management plan results in a project schedule that is too long. If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do? A. Fast track the project. B. Level the resources. C. Crash the project. D. Perform Monte Carlo analysis.
18. Which of the following processes includes asking team members about the time estimates for their activities and reaching agreement on the calendar date for each activity? A. Sequence Activities B. Develop Schedule C. Define Scope D. Develop Project Charter
21. You are a project manager on a US $5,000,000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can he worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities? A. Precedence diagramming method B. Arrow diagramming method C. Critical path method D. Operational diagramming method
22. You are a project manager on a US $5,000,000 software development project. While working with your project team to develop a network diagram, your data architects suggest that quality could be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with an article from a leading software development journal. Which of the following BEST describes this type of input? A. Mandatory dependency B. Discretionary dependency C. External dependency D. Heuristic
23. Based on the following, if you needed to shorten the duration of the project, which activity would you try to shorten? A. Activity B B. Activity D C. Activity H D. Activity C
The critical path is 16 (Start, C, E, H, End). Many people immediately look for the longest duration activity on the project to cut. Here activity D is the longest, at 10 weeks. However, that activity is not on the critical path, and cutting it would not shorten the project’s duration. You must change the critical path. In this case, both activity C and activity II are on the critical path. If you have a choice, all things being equal, choose the earlier option. Therefore, activity C is the best answer.
Start, A, C, E, F, End 107
Start, A, C, D, End 105
Start, B, D, End 55