What is Critical path analysis?
is a technique used to identify the order in which all activities need to be completed when planning a complex project.
What is The earliest start time (EST)?
the earliest the following activity can possibly start.
What is The latest finish time (LFT) ?
the latest an activity can finish without delaying the whole project.