List the scope management processes and their corresponding process groups!
What is the done in requirements collection techniques called nomimal group technique, multi-criteria decision analysis, affinity diagrams, benchmarking and context diagrams?
What is the difference between tasks and activities?
Tasks are smaller pieces of work that make up activites. PMI expects management on the activity level only!
What are control accounts?
Control accounts aggregrate data concering costs, schedule and scope at a higher level than low level work packages. Each workpackge is assigned to only one control account
List seven facts about the WBS to remember for the exam!
The WBS…
What is the difference between WBS and decomposition?
WBS is the means to do decomposition, i.e. the tool.
In what way differ control quality and validate scope?
In control quality the quality department checks to see if the requirements for the deliverable are met, in validate scope the customer checks and accepts the deliverable.
Validate scope can be done during closing a phase/the project and as part of monitor and control.
Which three artifacts are part of the scope baseline?