The purpose of prequalification of bidders is …
…to select only those contractors who meet certain standards of reliabilty, experience, financial stability, and performance
Prequalification of contractors is based on…
…information submitted by contractos concerning their financial qualifications, personnel, experience, references, size bonding capability, and any special qualities that make them partcularly suited for the project under constructions
The two primary ways to notify proespective bidders…
1) advertising in newspapers or trade journals
2) invitation to bid
With and advertisement for bids, the following information is published in one or more newspapers…
addendum
pre-bid conference
After bids have been opened, a decision of awade is typically made after…
…10 days
if all the bids exceed the project budget and the Owner-Architect Agreement fixes a limit on constriction, the owner has one of four options…
1) to rebid (or renegotiate if a negotiated contract)
2) to authorize an increase in the construction cost and proceed with the project
3) to work with the architect in revising the scope of the project to reduce construction cost
4) to abandon the project
bidding documents usually include the following…
which AIA document is often used as instruction to bidders?
AIA Document A701
bidder’s representations
instructions to bid usually contain…
After the award of the bid, the contractor must submit what to the archtiect
Bid security
If the successful bidder does not enter into an agreement…
the bid security may be retained to compensate for the difference between the low bid and the next lowest bidder
performance bind
because a performance bond only ensures completion of the project, but does not guarantee payment for labor and materials, what must an owner obatin in addition to a perofrmance bond?
-labor and material bonds
advantages of alternates in bids?
unit prices
Which of the following methods of bidding is required on most projects for which government funds are to be used?
public
Which of the following project delivery methods always requires preparation of several individual bid-document packages?
fast track
In developing a list of bidders for a private project, the architect’s role is to
recommened qualified contractors
After considering all bids, the owner favors a bid with irregularities. According to AIA Document A701, Instructions to Bidders, the owner
a) has the right to waive irregularities and accept the bid
b) has the right to extend the bidding period for corrections
c) must informally request corrections from the bidder
d) must only consider bids without irregularities
a) has the right to waive irregularities and accept the bid
. Which of the following is an appropriate agenda item for the prebid conference?
a) Occupancy-permit procedures
b) Notification of future addenda
c) Pre-commissioning procedures
d) Status of change orders
b) Notification of future addenda