Case Study
Why was JCT D&B 2016 selected? Any other options considered like NECC3?
Case Study
How were the liquidated damages of £350/week/unit calculated?
Case Study
Your role was procurement of consultants?
• Yes I assisted the client in seeking fee proposals for the likes of surveys/ reports required for the planning application for example a transport consultant and environmental consultant.
My role was to issue enquiry letters to a minimum 3nr consultants for each discipline. Review them on return and present the information to my client.
My client undertook the formal appointments.
• Is now Find a Tender service e-tendering portal accessed through Gov.uk website.
Case Study
You mentioned in the write up that you formed the Procurement Strategy. What options did you consider, and what why was it your recommendation?
• Recommendation – D&B using two stage tender. However, client due to unfamiliarity with two stage tendering instructed to progress the design and instruct a single stage tender.
Westhorpe Gardens:
How would you describe your clients value drivers on this project?
Westhorpe Gardens:
Value Engineering: What was your role in this?
Case Study
You note that you used a dropline on your pre-contract delivery programme for this scheme. What information does a dropline on a construction programme give you and what advice have you given you client in relation to what the dropline is highlighting?
Case Study
You mention that you sometimes found it difficult dealing with assertive personalities on the project, how did you have to adapt your personality and leadership style to effectively deal with these situations?
Democratic - to Autocratic (firm but fair)
Case Study
What studies/assessments were used to determine that the refurbishment of the existing block was unviable?
• Prior to my involvement however I understand my client undertook condition surveys and feasibility assessments on refurbishment vs regeneration.
Case Study
How do you ensure that all of the tenders are compared on a like for like basis
Quality – review against scoring matrix in ITT (look for any exclusions to inform QS)
Cost – QS Same CSA issued for costing (queries and normalisation process)/ ITT
1) Look for any errors , anomalies , conflicts – raise questions
2) normalisation process – (average of costs, cost plan) – questions against high / low
Case Study
You mention under achievements flagging that a Covid clause could be added under contract. What’s the benefit of this and would the contractor be entitled to EOT / L&E for covid delays in an unamended JCT D&B contract.
Benefits
• Makes clear what should be done if the event re-occurs – careful drafting
• Protect parties from Covid-19 is no fault of individuals and every party potentially stands to be protected from losses and inconvenience as a result of events that are beyond their control.
Unamended JCT D&B 2.26.14: “force majeure”. – Relevant Event
Not clearly defined.
‘The only steer given by the courts is that force majeure is commonly found to be an event beyond the control of the party seeking to rely on it, must not have been foreseeable at the date of the contract and must be the sole cause of non-performance’
Case Study
This all happened in 2020, so can you give me an example of how you’ve used this experience to help any of your current projects?
Yes Colville 2C which had some similar complexities and constraints – I stressed how having a contractor onboard could assist with some of the issues.
Case Study
What’s the risk of having the contractor on board earlier?
Case Study
If Phase 1B is undertaken earlier, what are the contract impacts? If the Contractor submitted a cost.
• Phase 1b was a separate sectional completion in the contract. So I understand this was proposed to be agreed via a Deed of Variation to amend the possession on this section with no impact to the sum in the contract for this section.
KEY ISSUE 1
19. A) Why was your recommendation Option 2, given the competitive element would have been lost?
As my client had advised that one of there key aims was to meet the target funding deadline and start onsite this option was the least likely to impact programme therefore my recommendation.
B)Key Issued 1 Option 2: How did you intend to manage that to ensure a premium was not added?
Advise client to instruct the QS to update the cost plan to include this phasing. This and the tender returns could then be used as a comparable/ benchmarking against the negotiated cost. Also issue them updated CSA template to price this on.
Key issue 1 ) How long was the tender extended for and did this have any ramifications on your Client’s key driver of a start on site date in July 2020?
Case Study
What documents were included in the tender?
Case Study
Why is there a potential cost impact for phasing?
• Additional programme and management time which may increase preliminary costs and requirements to remobilise, welfare etc.