What is Insurance Option A:
Contractor takes out and maintains joint names all risks insurance of the works
What is Insurance Option B:
Employer takes out and maintains the joint names all risks insurance of the works
What is Insurance Option C :
the Employer to maintain a joint names policy for existing structure
Letter of Intent main types
1) Comfort Letter - not legally binding
2) Agreement to spend - Legally binding
3) Recognition of entering contract - Legally binding
Commerce Road - Client chose not to Levy LD’s how would this be recorded
In the Final Account Statement
Give an example of when you have advised a Client on Contract Selection.
You mentioned that the Contractor failed to complete works by the Contract Completion Date on Commerce Road. What did you do?
Issued Certificate of Non Completion, and notice that Employer may wish to levy LD’s
You’ve mentioned JCT in your write up, but what other Suites of Contract are you aware of?
What are the differences between a JCT and NEC?
Can you give me an example of some of the Bonds you are aware of? Have you experience any of them?
On Colville Phase 2C, what was the procurement route recommended in your report, and what were the principle reasons?
On Varcoe Road, did you have to issue a payment notice even though it was a nil cost.
Yes as the contractor had submitted an application for Payment, no this was required in line with the Construction Act.
On Varcoe Road, what works were complete (approx. value) before the performance bond was in place?
Demo had commenced and piling, I advised my client of there available options and risks associated with doing so.
Varcoe Road: Also, what contractual terms were your advice based on, was it an amendment to the standard contract?
I was not party to agreeing the contract terms, however yes there was an amendment.
On Varcoe Road, was there any other alternatives, rather than issuing a nil valuation?
On Commerce Road, how were LD’s deducted?
Client chose not to levy LD’s. However I understand if they were to the process would be;
• Issue Certificate of Non Completion
• Notice Employer may levy LD’s
• Employer issue notice that they will levy LD’s
• Pay Less Notice levying the LD’s no later than 5 days before final payment date
Can you tell me some pre-contract advice you would give to a Client about LDs?
That there calculation should be based on actual forecasted loss.
Can you give me an example of how you have assessed an Extension of Time?
Can you explain how a Collateral Warranty works and why you would advise a Client to obtain one?
Can you explain the difference between Sectional Completion, Partial Possession and Early Use?
What are the disadvantages of design and build
What is a relevant event?
A relevant event is an event that causes a delay to the completion date, which is caused by the client, or a neutral event not caused by either party.
Name some relevant events?
Exceptionally adverse weather.
Failure to provide information.
Statutory undertaker’s work.
Force majeure (such as a war or an epidemic).
Loss from a specified peril such as flood.
The supply of materials and goods by the client.
National strikes.
Changes in statutory requirements.
What is a relevant matter
A relevant matter is a matter for which the client is responsible that materially effects the progress of the works. This enables the contractor to claim direct loss and / or expense that has been incurred.