What does the red tick mean on the Slide for Key Issue 1?
It means that although lacking a formal tender process, Option 1 still achieved a degree of certainty for the client through:
* Measured rates
* A trusted and known contractor
* Benchmarking against industry-recognised rates e.g. BCIS, SPONS
You mention cracks in the masonry due to saturation. What else could have caused these, and how did you discount other possibilities?
If you had pursued Option 1, how would you have worked out abortive costs?
If you had pursued Option 2, what would be the implications of having 2 contractors on site under different contracts, in terms of the CDM Regulations?
For Option 3, who decided on the measured rates? How were they established? How did you check costs?
What did you need to consider in re-rendering the walls in terms of compliance with Part-L of the Building REgulations?
How did you quantify Prov Sums in the Schedule of Works?
These were based on a budget estimate of the likely works involved. Where possible, they were based on a known rate and scaled to the likely quantity required.
What detailing did you identify to the roof/wall-plate junction to achieve adequate thermal qualities?
Ask Mat?
How did you ensure design quality with the negotiated works?
What is the contractual status of progress meeting minutes?
How did you go about formalising the additional time spent on the structural works? Was there an EOT granted? How was this agreed and formalised?
What are Relevant Matters in JCT Contracts?
What are some examples of Relevant Matters?
What is a Relevant Event?
What is the difference between defined and undefined provisional sums?
Where does the risk lie with defined and undefined provisional sums?
How was the structural engineer appointed and how did you advise the client on the terms of that appointment? Scope of services, fee basis, form of appointment? Direct appointment to client or subconsultant to PMP? What would be the risks associated with the latter?
How did you deal with any issues relating to the neighbouring properties and works that might impinge upon them?
Wyh was the client’s maintenance contractor not used to complete opening up of the ceiling / boarding as part of the investigation stages, given the presence of roof leaks and building generally?
You acted as Contract Administrator and Principal Designer on the same project. What issues might this create and how might you overcome them?
Which standard form of contract was administered, if not JCT? Were the procurement options and suitable form of contract advised to your client beforehand?
Can you give me an example of how the Framework Agreement differs from a standard JCT Minor Works?
What design and construction improvements were considered and ultimately made to the roof and the rest of the relevant areas of building fabric in undertaking the works and why?
Widening of valley gutters - to improve drainage provision.
Widening of parapet outlets - as above.
Installation of lay-boards to increase height of upstands.
Encapsulation of parapet copings with waterproofing inc drip detail.
Replacement of waterprooinf to flat roof and additio of insulation.
Strengthening works to external walls..
How did you manage asbestos during the project, and during investigative works?