What happens at Practical Completion?
What is Sectional Completion?
Do works have to be totally complete at Practical Completion?
No, it is down to the opinion of the Contract Administrator under JCT contracts. Normally for ‘De Minimus’ works to be outstanding, but nothing that restricts the employer’s beneficial occupation of the building.
Mears vs Costplan is relevant piece of case law - is the defect ‘trifling’ in nature.
What is Partial Possession?
What is a Collateral Warranty?
What are the common terms within a collateral warranty?
What is an Letter of Intent and When is it Used?
What are JCT Minor Works Insurance Clauses?
What are JCT Intermediate and Standard Building Contract Insurance Provisions?
What is role of Contract Administrator under a Traditional Contract?
What must be in place before LADs can be deducted?
Can an employer still claim LADS if no loss suffered?
Yes
What is a typical statutory ‘Limitation Period’ in a construction contract?
Why did you use the JCT IC at Cobden Avenue? What are the differences between a JCT IC and MW Contract?
You drafted a Letter of Intent for Francis Avenue. What needs to be included in this and what are the legal implications?