Why did you use the JCT Intermediate Building Contract and not the Standard Building Contract?
Why did you use the JCT Intermediate Building Contract and not the Minor
Works?
Why did you prepare a Stage 4 Cost Plan? What was the benefit?
Why was a BOQ the most suitable form of pricing documents?
What are the steps involved with producing a BoQ?
1) Separate the works out into key elements or packages e.g. substructure, frame, roof, external walls
2) Create a take off list for each elements identifying from the design information all the works items that need to be measured and billed (in
accordance with NRM2)
3) Allocate the elements to certain colleagues to share the workload
4) Measure measure and measure (in accordance with NRM2) - this could involve back and forth query and answer sheets with the design team
5) Input measure in BQ format using software such as Masterbill or CATO
6) Thoroughly quality check the Draft BQ and associated measures to ensure everything is correct and has been picked up, and is fully coordinated with the design information.
7) Finalise the BQ to form the pricing document for the tender
What were the Tender documents you issued?
1) Design Information
2) Instruction to Tenderers
3) Project Particulars
4) Contract Particulars
5) Pricing Document (i.e. BQ)
6) Form of Tender - which the tenders fill out and sign it includes their details, price and programme duration
7) Prelimianies and workmanship documentation
8) Supporting Docs - including
- Pre Construction Information Pack, -Contractor Design Portions,
- Bond requirements,
- Planning information
- draft example of Sub-Contractor Warranty required for the Employer
What is a Pre-Construction Information Pack?
The Pre Construction Information Pack (PCIP) is a document which provides the information already in the Client’s possession, or which is reasonably obtainable, to relevant CDM Duty Holders, such as Designer(s), Contractor or Principcal Contractor.
The client is responsible for providing this, although it is usually completed by the CDM pronciple designer.
Includes information such as:
- Description of poject
- Clients management requirements
- Envrionmental restrictions
- Health and Safety Information and requirements
- Hazards or risks
- Construction Phase Plan
What is a Construction Phase Plan?
A Construction Phase Plan is a key document that details the health and safety risks associated with the construction phase of the project and the control measures that will be implemented to minimise risks or where possible, eliminate them.
What were the Contractor Design Portions?
a) Precast concrete staircases:
b) Precast concrete upper floors
c) Beam & block floors
d) Structural connections, including thermal break connections
e) Secondary steelwork
f) Light gauge metal infill studwork to external wall construction
g) Architectural metalwork, balustrades, including fixings
h) Lintels
i) Piling
j) Roof purlins, metal deck system and associated detailing
k) Metal louvered fence to plant room roof
l) Roof hatch and access ladder
m) Proprietary masonry support systems and details
n) All proprietary cladding and curtain walling
o) Lift
p) Final coordination of mechanical and electrical installations
What was the projects GFA?
1,182m2
What is the £/m2 of the project? How does this compare to BCIS analyses / average prices?
What is the £ / classroom?
Approx £330K per classroom (based on overall project cost)
What is the £ / pupil?
The projected equated to approx £13.5K per pupil (based on overall project cost), which was well within the Department For Education (DfE) benchmark data, rebased to Kent (approx £27K per placement for permanent expansions to existing secondary schools).
- This showed Value of Money for the project
How did the you benchmark the cost of the project to demonstrate value for money (VFM)?
How did you account for risk in your cost plans?
Design Development Risk
Construction Risk
Employer Risk
How did you calculate inflation estimates?
Using tender price inflation data from BCIS. And calculating this for the require timescales associated with the cost plan and project
What problems did you encounter when shortening the pre-contract programme and how did you mitigate these?
If the contractor submitted after the tender deadline what would you do?
Tenders must ensure they submit tenders within the timescale set out in the tender documents. If a late tender was received, I would discuss this with my client and it would be up to their desecration whether to accept the late tender or not.
How did you assess the tenders received?
How did you go about the VE process?
Must haves - elements that are key to the brief of the project.
Should haves - elements that are good practice and of inherent value for the project
Could haves - elements that are potentially achievable within the project budget.
Won’t haves - elements which need to be avoided; from lessons learned on previous schemes
What were the potential VE savings that could have been obtained?
Explain the contractual process for dealing with an EOT?
Explain the contract process for dealing with a Loss & Expense Claim?
Relevant events include:
- Variations or client changes
- Failure to give contractor possessions of the site
- Delays receiving instructions
What was the Relevant Matter on your project?
Variations - drainage rupture within the existing school required additional works and the client also instructed a change to the external works (new access arrangements)