What are the names of each stage identified in the RIBA Plan of Work?
Stage 0 - Strategic Definition
Stage 1 - Preparation and Briefing
Stage 2 - Concept Design
Stage 3 - Spatial Coordination
Stage 4 - Technical Design
Stage 5 - Manufacturing and Construction
Stage 6 - Handover
Stage 7 - Use
Why do we have the RIBA Plan of Work?
What is a programme, and why do we need one for a construction project?
What information does a programme typically show?
What is programme float?
Float is the amount of time an activity can be delayed without delaying the subsequent activity or critical path.
What is lag between activities?
When the first activity completes and there is a delay before the second activity starts, this is called lag.
Can you provide a working example of lag on a new build project?
Once a concrete foundation is laid, there will be lag prior to erecting steelwork (to allow the concrete to cure/harden)
What is the critical path on a programme?
Can critical path activities have float?
Critical path activities have no float. If critical path activities are delayed, the overall completion of the project will be delayed.
What are milestones?
A project milestone is a task of zero duration that shows an important achievement in a project.
Please provide examples of typical programme milestones for a new build construction project?
What is the difference between a jagged and a straight drop line on a programme?
Jagged drop line:
- Progress as a percentage is entered for each task. This shows activities which are on, behind or ahead on the reporting date
Straight drop line:
- After progress is entered, the programme is rescheduled so each task sits on the progress reporting date (this straightens the drop line).
- It is useful to determine the impact on the critical path.
How would you put together a programme for a new project?
What is a concurrent delay?
Two or more delays caused by different parties occur independently of each other, but during the same period.
What is the benefit of assigning resources to specific programme activities?
What is acceleration in programming terms?
Acceleration means completing the works in a shorter period or mitigating some form of delay (and completing on the original date).
What options may be considered to facilitate acceleration?
What is a Gantt Chart?