What is the most efficient Plan?
In terms of cost a simple square or rectangle is the most efficient.
A circular plan is the most efficient in terms of wall/floor ratio, however the difficult shape impacts upon internals making it less efficient.
What other design efficiency’s are you aware of?
Net Internal Area - total usable floor area excluding toilets, corridors, stairs ,etc.
What traditional construction methods did you base your cost model of?
Pad foundations in a grid format.
Strip foundations to the perimeter.
Ground bearing slab
Steel frame based upon 60kg/m2
Composite metal deck - Upper floor
Kingspan cladding to roof
External walls - Masonry and cladding
Glazing assumed at 15% of facade
What is the difference between a CAT A fit out and a CAT B fit out?
Cat A fit out is a developers fit out and creates basic functionality so this will include RAFs, Suspended ceiling, carpet tiles, power supplies, etc.
Cat B fit out is a tenants fit out which is bespoke to them so this will usually include working with interior designers, this includes furniture, internal partitions, etc.
What factors should be considered when choosing between a CAT A and Cat B fit out?
Lease Terms
Budgets
Tenant Requirements
What does the wall to floor ratio tell me?
It tells you the amount of wall area in comparison to floor area, the closer the formula is to 0.40 is deemed very efficient.
If it is high and inefficient this shows the additional costs facade costs and potentially foundation costs, etc.
Why does an irregular building shape create inefficiency’s?
This is due to the increased building perimeter and design complexities.
What makes the two Storey design more efficient?
Reduced overall building footprint
Costs for the roof and foundations are not duplicated
Utilities can be designed more efficiently
What was the clients main requirements on this site?
Parking Provisions
Cost - Cost limit
What are the benefits and disadvantages of a steel frame?
Advantages - quick erection on site, long spans, sustainability benefits, lightweight (reduces foundations requirements), manufactured offsite.
Disadvantages - Maintenance, additional fire protection, large items to be transported, volatile costs.
What is asbestos?
Asbestos is made up of fibrous minerals that is harmful to humans, causing lung cancer, asbestos was used due to it being heat and corrosion resistant.
What was the cost model you used?
The cost model followed an elemental cost plan format with a number of assumptions.
Foundations - Strip to perimeter, Pads on a 7.5m x7.5m grid to the perimeter grid, central spine of a hit and miss basis.
Steel - single storey based upon 40kg/m2, two storey based upon 60kg/m2
Upper floor - Composite concrete metal deck
Roof - Kingspan cladding
External walls - built up cladding and masonry/timber cladding
Glazing - based upon a percentage.
Office fit out was based upon a cost per m2 rate
How did you advise the client on reducing the risk of the site?
What did the ground conditions report tell you and what impact can this have on costs?
What was the main challenge you faced when advising on the design options?
What were the key cost drivers across the three options?
How did site constraints influence your recommendations?
Why was cost per m² such an important metric in this case?
How did you ensure your feasibility advice aligned with the client’s priorities?
Talk me through how you prepared your Order of Cost Estimates.
What assumptions did you make in your elemental cost model?
assumptions made were based upon discussions with the architect and the engineers.
Eaves height
Foundation types and locations
Steel tonnage
% of glazing
How did you validate the accuracy of your cost model at feasibility stage?
To validate the accuracy of the cost model i compared the cost per m2 against benchmark data.
The two contractors taken forward - HQ tender return worked out £3029m2 - £3319m2.
How did you explain the difference between overall cost and cost per m² to the client?
Cost per m2 (The Benchmark): I explained in the early design stage to get a rough idea of budget feasibility. It represents the average cost for basic construction but often misses specific site conditions, high-end finishes, or professional fees.
The overall cost is the total amount, and what the likely sum will be paid to complete the project.
What risks are associated with cost modelling at early design stages?
Low level of information
Scope creep
Assumptions