What is a contract?
Contains a set of promises that each party has made to the other.
What are the principles of a contract?
Offer
Acceptance
Intention
Consideration
Lawful
What is under hand and a deed?
It is how a contract is executed.
Under hand is when the limitation period for initiating proceedings is 6 years whereas a deed is 12 years
What are express terms and implied terms?
An express term is defined in the contract, Implied terms are not defined in the contract
What is quantum meruit?
This is where a reasonable sum is paid for the services rendered or work undertaken if the amount due is not stipulated in the contract.
Can you give an example of an Implied term?
An implied term is assumed to be part of the contract for example employers duty to cooperate with the contractor
What is Privity of contract?
A person who is not party to a contract cannot gain any benefit by suing on it, nor can they suffer any detriment by being sued on it.
What is an example of privity of contract?
What if the client tells you LADs are £100k a week?
LADs figure are based on a genuine pre estimate of loss and if they can’t prove the genuine financial loss it is likely to not be enforceable.
What is an extension of time?
EOT adjust the completion date and relieves the contractor to pay LADs.
What are LADs?
LADs are a genuine pre estimate of loss should the contractor not meet the completion date.
What must be in place before Lads can be deducted?
Withholding notice
A non completion certificate
What if the employer actually suffered no loss or damage?
The damages can still be deducted at the value stated in the contract
What are the benefits of being able to grant EOT?
It relieves contractor liability for LADs for delay they have not caused
It enables another completion date to be set.
What happens when time is at large?
There is no set completion date
LADS cannot be claimed and contractor has obligation to complete works in reasonable time
What are the relevant events?
Variations
Deferment of possession of the site
Suspension by the contractor for non payment
Strike
Averse weather
Force Majeure
Terrorism or civil commotion
What are the main elements found in a interim valuation?
Preliminaries
Measured Work
Mats on site and mats off site
Loss & Expense
Retention
What needs to be in place to include payments for materials on site?
Materials should be for the works
Materials should be on programme
Should be protected
What needs to be in place to include payments for materials off site?
Vesting certificate
Correct Insurances
Materials are clearly marked and stored together
MOS bond has been provided if required
What is a vesting certificate and what would be included?
A vesting certificate is a legal document confirming that ownership of goods, materials, or equipment transfers from a supplier or contractor to a purchaser upon payment, even if the items are stored off-site and not yet delivered.
Materials off site should be listed within the contract.
Includes:
Reference - number/date of issue
Description - Details of product
Project info - Clearly named project
Proof of ownership
Insurance details
Storage location
reference to payment details
What is a retention of title clause?
Where a sub contractor retains ownership of materials until they are paid for by the contractor.
Highlights the importance of a vesting
How do you evaluate interim valuations?
Inspect site and attach percentages against the work, review against cashflow, value time related and fixed prelims, etc.
How do stage payments work?
Stages and values are set out in the contract particulars
stages are usually set when certain elements of the works are complete for example the foundations.
What is an interim certificate conclusive off?
Interim certificates do not carry any contractual significance apart from the final one.